Inspections for the day of: Wednesday, March 7, 2007.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR07-00020 INSP-Alarm Testing3/6/20073/7/20073/8/2007 12:39:44 PMPPASS
Fire alarm work passed inspection.
FIR06-00667 INSP-Alarm Testing3/6/20073/7/20073/8/2007 12:38:25 PMPPASS
Items on previous c/n have been field verified for compliance, final inspection passed.
FIR07-00175 INSP-Final Inspection3/7/20073/7/20073/7/2007 3:21:40 PMPPASS
FA permit finaled.
FIR05-00403 INSP-Final Inspection3/7/20073/7/20073/7/2007 3:20:35 PMPPASS
Fire sprinkler passed final inspection, permit finaled.
FIR05-00269 INSP-Final Inspection3/7/20073/7/20073/7/2007 3:19:34 PMPPASS
UG fire supply line permit finaled.
FIR07-00173 INSP-Final Inspection3/6/20073/7/20073/7/2007 3:18:27 PMPPASS
Final fire alarm passed inspection, permit finaled.
FIR07-00175 INSP-Alarm Testing3/7/20073/7/20073/7/2007 3:17:20 PMAPASS
Fire alarm work passed field inspection, noted the changed EOL locations to be reflected on as-built drawings, also need to provide signage on the door to the FACP room.
FIR07-00064 INSP-Final Inspection3/6/20073/7/20073/7/2007 3:14:56 PMANR
Not ready for inspection per contractor.
MIS07-00041 FIR-Final3/6/20073/7/20073/7/2007 9:50:44 AMAPASS
Life safety inspeciton passed. Noted locking hardware at the hallway door to the shared restrooms to be removed prior to structural final as agreed.
FIR05-00880 INSP-Final Inspection3/6/20073/7/20073/7/2007 9:15:24 AMAPASS
Final fire alarm inspection passed, permit finaled.