BLD12-00337
| FIRE-Final Inspection | 3/7/2012 | 3/7/2012 | 3/7/2012 5:21:56 PM | P | NR |
|
|
Project related fire alarm permit has not been issued at this time, currently in the "review" status.
|
BLD11-01142
| FIRE-Conference | 3/7/2012 | 3/7/2012 | 3/7/2012 5:18:55 PM | P | DONE |
|
|
Final inspection scheduled 3/8 PM.
|
FIR11-00496
| INSP-Sprinkler Rough-in | 3/6/2012 | 3/7/2012 | 3/7/2012 5:17:56 PM | A | PART |
|
|
See approved plan set for annotated locations including the 3rd floor north wing tenant and common corridor, 1st and 2nd floor north wing tenant showers, 1st and 2nd floor north wing common corridors, 2nd and 3rd floor south and north stairways.
|
FIR11-00448
| INSP-Sprinkler Rough-in/Hydro | 3/6/2012 | 3/7/2012 | 3/7/2012 5:06:33 PM | A | PART |
|
|
Inspection for cover at the new drop ceiling in the SW stair completed.
|
FIR11-00575
| INSP-Alarm Testing | 3/6/2012 | 3/7/2012 | 3/7/2012 5:02:25 PM | A | PART |
|
|
Today's inspection included under floor SD's at zones 4 and 5, clean link HSSD's at zones 1,2,3 and 4, HEPA shutdown at zones 1 thru 6 including program operations, duct detectors at mechanical mezzanine 43 and mech. room 44. Initiating device addresses and functionality tested okay. Noted one SD above the FATC in mech. room 44 to be relocated to the deck, MAU's at mech. mezzanine are not ready for shutdown test, discussed locations of duct detectors at the floor level east electrical room.
|
FIR11-00598
| INSP-Final Inspection | 3/6/2012 | 3/7/2012 | 3/7/2012 4:42:04 PM | A | NR |
|
|
Check status Phone #: ###-#### >> Inspection requested via web by Jeff Walton
|
FIR12-00037
| INSP-Final Inspection | 3/7/2012 | 3/7/2012 | 3/7/2012 4:41:16 PM | A | PASS |
|
|
Inspection passed. Fire alarm permit finaled.
|