ESC13-01045
| BMP Violation | 3/7/2014 | 3/7/2014 | 3/7/2014 2:06:53 PM | P | PEND |
|
|
Met RP Justin onsite. He has until Monday morning 3/10 to acquire a general ESC permit for 440 Whisperwood and is to be responsible for grading and clean up for the mess made due to activities at this site. If not, a SWO and/or hold will be put on Sunrise Homes.
|
ESC13-00817
| Aging Inspection | 3/7/2014 | 3/7/2014 | 3/7/2014 2:03:01 PM | | PASS |
|
|
Finaled.
|
ESC13-00817
| DOC - Permit Finaled | 3/7/2014 | 3/7/2014 | 3/7/2014 2:02:37 PM | P | PASS |
|
|
House complete and landscaped/stabilized. All permits finaled.
|
ESC13-00603
| Aging Inspection | 3/7/2014 | 3/7/2014 | 3/7/2014 1:32:47 PM | | PASS |
|
|
Finaled.
|
ESC13-00603
| DOC - Permit Finaled | 3/7/2014 | 3/7/2014 | 3/7/2014 1:32:29 PM | P | PASS |
|
|
Maverik sign is installed. Seperate building ESC permit already finaled. All ESC conditions met.
|
ESC13-00918
| General Inspection | 3/7/2014 | 3/7/2014 | 3/7/2014 11:56:45 AM | | PASS |
|
|
See ESC13-00806. Silt fence in good condition. RP making corrections for main site.
|
ESC13-01167
| Site Preparation | 3/7/2014 | 3/7/2014 | 3/7/2014 11:53:23 AM | P | PASS |
|
|
Discussed site with RP and excavator Steve Brunell. BMPs including perimeter wattles and entrance are installed.
GC Matt Brown is pulling a general ESC permit for stockpiling/staging at 525 Orion to have permission to use that parcel. No ESC plan required for staging area.
Site is ready for excavation.
|
ESC12-01066
| Tracking Control | 3/6/2014 | 3/7/2014 | 3/7/2014 11:21:42 AM | A | FAIL |
|
|
916 Park making track out. ACHD working on it. Will re-inforce as necessary
Went on site to discuss with RP Kent. He stated they swept yesterday but this morning's operations caused more track out to Front Street.
Corrections issued: 1. Improved construction entrance. 2. Install DI bag (2nd request)
He stated DI bag will be installed today and that more rock will be ordered for the entrance. Pictures of track out taken @ 11:15 AM.
|
ESC13-00773
| General Inspection | 3/7/2014 | 3/7/2014 | 3/7/2014 10:52:48 AM | | FAIL |
|
|
There appears to be a spill of green antifreeze into the gutter behind the Boise Basin Electric work van. Followed spill about 50-75 feet in north gutter.
Called Clint RP. He is on his way to apply spill absorbent and discuss with contractor.
Waited for RP to arrive. We believe spill is from cement pumping truck which may have leaked hydrauic oil. Clint started sweeping while I was there, applying spill absorbent, and called Brundage Bone to come assist in clean up.
Positive response. Will check back for clean up conditions.
|
ESC13-00774
| General Inspection | 3/7/2014 | 3/7/2014 | 3/7/2014 10:34:32 AM | | PASS |
|
|
WIP. No violations.
|
ESC13-00449
| General Inspection | 3/7/2014 | 3/7/2014 | 3/7/2014 10:09:15 AM | | PASS |
|
|
Called RP Melanie at K2 Construction to inquire if project is still in the works. It is currently on hold, pricing just went back to Dennis Dillon, and plan is too start work by end of March 2014. I informed K2 that they should request an extension so the BLD permit does not get closed.
|
ESC13-00806
| Conference | 3/7/2014 | 3/7/2014 | 3/7/2014 9:42:54 AM | P | DONE |
|
|
GC Randy returned call to discuss corrections and plan.
1. Construction entrance will be repaired by Monday. 2. Road and sidewalk will be swept. 3. Stockpile on ESC13-00918 is to be removed next week. The lot will then be used as the staging are for remaining project. Current staging area will be cleaned and regraded per agreement with Randy.
The site will be in compliance by end of next week. Site has good record of making corrections so far. Will check next week.
|
ESC14-00153
| Site Preparation | 3/6/2014 | 3/7/2014 | 3/7/2014 9:35:09 AM | A | PASS |
|
|
Bill Phone #: ###-####
Garage to be built on existing pad adajacent to house, approximately 50 ft from Kootenai. MS4 located at Kootenai & Roosevelt about 50 m down the street. No dirt will be brought in or removed. Discussed project with GC Bill who scheduled inspection. Approved. Low risk.
|
ESC13-00269
| General Inspection | 3/7/2014 | 3/7/2014 | 3/7/2014 8:41:42 AM | | PASS |
|
|
Disturbed areas around the perimeter and where the job trailor was located are in the process of stabilization with hydroseeding in place. Will continue to monitor progress. No violations.
|
ESC13-01167
| Site Preparation | 3/6/2014 | 3/7/2014 | 3/7/2014 7:48:42 AM | A | CANC |
|
|
Talked with GC on 3/6 regarding inspection. Will call tomorrow.
rescheduled for the afternoon.
|