Inspections for the day of: Wednesday, March 7, 2018.
Number of inspections: 18
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Storey
TitleBLD-COM/RES INSPECTOR
Phone #794-9490
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD17-03622 BLD-Aging Inspection3/7/20183/7/20183/8/2018 11:03:47 AM PASS
BLD17-01222 BLD-Aging Inspection3/7/20183/7/20183/7/2018 3:42:14 PM PASS
wip
BLD17-00091 BLD-Energy code compliance3/7/20183/7/20183/7/2018 3:30:26 PMPPASS
Lee Scott Phone #: ###-#### exterior walls lobby 1st floor ok to cover.
BLD18-00597 BLD-Final3/7/20183/7/20183/7/2018 2:43:04 PMPPASS
need final Phone #: ###-#### Inspection requested via web by Chris Howell
BLD18-00597 DOC - Permit Finaled3/7/20183/7/20183/7/2018 2:42:51 PMPPASS
BLD17-00595 BLD-Final3/6/20183/7/20183/7/2018 2:21:29 PMPFAIL
call for lock box code// Brent Phone #: ###-#### remove door #18/ handrail bothsides of stair w/returns
BLD17-04180 BLD-Final3/6/20183/7/20183/7/2018 1:44:06 PMAPASS
roof is all done thank you Phone #: ###-#### Inspection requested via web by Sandra Daffer
BLD17-04180 DOC - Permit Finaled3/7/20183/7/20183/7/2018 1:43:42 PMPPASS
BLD18-00379 BLD-Footing3/6/20183/7/20183/7/2018 1:43:02 PMPPASS
Dave Phone #: ###-####
BLD16-02103 BLD-Final3/6/20183/7/20183/7/2018 1:16:45 PMPPASS
Call for escort - Ken Phone #: ###-####
BLD16-02103 DOC - Permit Finaled3/7/20183/7/20183/7/2018 1:16:34 PMPPASS
BLD18-00681 BLD-Conference3/7/20183/7/20183/7/2018 11:54:26 AMANR
Please check mechanical permit to see if signed off. If approved...please inspect for approve to insulate. Thank you. Phone #: ###-#### Inspection requested via web by Timothy Beaudoin no mech permit issued
BLD18-00307 BLD-Foundation3/6/20183/7/20183/7/2018 11:46:56 AMAPASS
Jeremy Phone #: ###-####
BLD16-02420 BLD-Final3/6/20183/7/20183/7/2018 11:46:40 AMAPART
Dave Phone #: ###-#### Dave Phone #: ###-#### Received call from project owner Dave O’Neal regarding request for TCO on a single unit while field inspector correction items (smoke alarm placement) are being corrected. Let Dave know that if the structural field inspector is equally supportive relative to other correction items that may exist from the structural field inspector are satisfactory; the fire/life safety inspection group is OK with a single tenant initiating the move in process while the subject smoke alarm issue is being resolved by the licensed electrician. Once device is relocated, a final inspection request can be made. Contacted fire life safety field inspector to notify of discussion with owner. / handrail extention to be resolved with planreview// note per fire
BLD16-02421 BLD-Final3/6/20183/7/20183/7/2018 11:46:18 AMAPART
Dave Phone #: ###-#### Received call from project owner Dave O’Neal regarding request for TCO on a single unit while field inspector correction items (smoke alarm placement) are being corrected. Let Dave know that if the structural field inspector is equally supportive relative to other correction items that may exist from the structural field inspector are satisfactory; the fire/life safety inspection group is OK with a single tenant initiating the move in process while the subject smoke alarm issue is being resolved by the licensed electrician. Once device is relocated, a final inspection request can be made. Contacted fire life safety field inspector to notify of discussion with owner. / handrail extention to be resolved with planreview// note per fire
BLD18-00562 BLD-Final3/6/20183/7/20183/7/2018 9:55:55 AMAPASS
call 20 mins before- Chelsea Phone #: ###-####
MIS17-00417 MIS-Aging Inspection3/7/20183/7/20183/7/2018 9:27:27 AM DEFR
ray is following up on the fire side.
BLD17-00091 BLD-Other3/6/20183/7/20183/7/2018 9:10:07 AMAPASS
shaft liner // Lee Scott Phone #: ###-#### stair lids and shafts in corridors ok to cover