PLM00-00289
| Final | 3/7/2000 | 3/8/2000 | 3/8/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/07/2000 at 12:01:59. Contact: . Final ok. 3/8/00 2:11:02 PM
|
PLM00-00601
| Sprinkler (Final) | 3/7/2000 | 3/8/2000 | 3/8/2000 12:00:00 AM | A | PASS |
|
|
mike ###-#### backflow Sprinkler final. 3/8/00 2:10:49 PM
|
PLM00-00527
| Water and/or Sewer | 3/7/2000 | 3/8/2000 | 3/8/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/07/2000 at 15:13:40. Contact: ###-####. sewer & water final. 3/8/00 2:10:56 PM
|
PLM99-02711
| Final | 3/7/2000 | 3/8/2000 | 3/8/2000 12:00:00 AM | A | PASS |
|
|
Dale ###-#### final ok. 3/8/00 2:11:07 PM
|
PLM99-03708
| Final | 3/8/2000 | 3/8/2000 | 3/8/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/08/2000 at 09:03:58. Contact: ###-####. Final ok. 3/9/00 9:08:51 AM
|
PLM99-04235
| Final | 3/8/2000 | 3/8/2000 | 3/8/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/08/2000 at 09:05:14. Contact: ###-####. Final ok. 3/9/00 9:08:56 AM
|
PLM00-00606
| Final | 3/8/2000 | 3/8/2000 | 3/8/2000 12:00:00 AM | P | PASS |
|
|
###-#### Leo Water heater final. 3/9/00 9:09:10 AM
|
PLM00-00219
| Final | 3/8/2000 | 3/8/2000 | 3/8/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/08/2000 at 10:53:08. Contact: ###-####. Final ok. 3/9/00 9:09:03 AM
|