MEC00-04296
| Rough-in | 3/7/2001 | 3/8/2001 | 3/8/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/07/2001 at 17:04:21. Contact: ###-####.
|
MEC00-04296
| Pressure Test | 3/7/2001 | 3/8/2001 | 3/8/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/07/2001 at 17:05:30. Contact: ###-####.
|
MEC00-04297
| Pressure Test | 3/7/2001 | 3/8/2001 | 3/8/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/07/2001 at 17:05:39. Contact: ###-####.
|
MEC00-04297
| Rough-in | 3/7/2001 | 3/8/2001 | 3/8/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/07/2001 at 17:06:14. Contact: ###-####.
|
MEC00-04434
| Final | 3/8/2001 | 3/8/2001 | 3/8/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/08/2001 at 06:56:10. Contact: ###-####.
|
MEC01-00681
| Rough-in | 3/8/2001 | 3/8/2001 | 3/8/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/08/2001 at 09:37:38. Contact: ###-####.
|
MEC01-00681
| Pressure Test | 3/8/2001 | 3/8/2001 | 3/8/2001 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 03/08/2001 at 09:37:52. Contact: ###-####.
|
MEC01-00219
| Final | 3/8/2001 | 3/8/2001 | 3/8/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/08/2001 at 10:30:46. Contact: ###-####.
|