Inspections for the day of: Thursday, March 8, 2007.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEric Strole
TitlePLM/MEC-INSPECTOR
Phone #794-7913
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM07-00665 Water and/or Sewer3/8/20073/8/20073/8/2007 4:39:46 PMPPART
water line from street to house ok to cover, will do well disconnect at a later date.
PLM07-00456 Final3/8/20073/8/20073/8/2007 4:11:34 PMPPASS
Electrician should have power to Poin of Use water heater today. Would like inspection in late afternoon. Thank You Phone #: ###-####
PLM07-00646 Plumbing Rough-in3/8/20073/8/20073/8/2007 3:42:31 PMPPASS
Contact: Dan or Linda Phone #: ###-####
PLM07-00647 Plumbing Rough-in3/8/20073/8/20073/8/2007 3:42:18 PMPPASS
Contact: Dan or Linda Phone #: ###-####
PLM07-00606 Sprinkler (Final)3/7/20073/8/20073/8/2007 2:34:06 PMPPART
ok to cover, needs to put blow down tee down stream of dbcv & get tested & certified.
PLM07-00663 Sprinkler (Final)3/8/20073/8/20073/8/2007 2:17:53 PMPPASS
peter; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
PLM07-00662 Sprinkler (Final)3/8/20073/8/20073/8/2007 2:13:15 PMPPASS
peter; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
PLM07-00661 Sprinkler (Final)3/8/20073/8/20073/8/2007 1:59:04 PMPPASS
peter; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
PLM06-04181 Final3/8/20073/8/20073/8/2007 1:40:44 PMPPASS
craig; Phone #: ###-#### Internet Inspection Request from: Stacie Backus
PLM07-00609 Water and/or Sewer3/8/20073/8/20073/8/2007 1:28:28 PMPPASS
lupe; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt
PLM06-02344 Final3/8/20073/8/20073/8/2007 12:20:40 PMPPASS
craig; Phone #: ###-#### Internet Inspection Request from: Stacie Backus
PLM07-00488 Plumbing Rough-in3/7/20073/8/20073/8/2007 11:58:32 AMAPASS
ken - late morning; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
PLM07-00655 Plumbing Rough-in3/8/20073/8/20073/8/2007 11:29:44 AMPPASS
jeff; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
PLM05-03585 Final3/7/20073/8/20073/8/2007 11:01:35 AMAPART
Job # 2345 Phone #: ###-####-need dbcv tested and certifed for fire system, need a permit for dbcv on sprinkers & have tested & certified.
PLM07-00626 Sprinkler (Final)3/7/20073/8/20073/8/2007 10:07:00 AMAPASS
paul; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
PLM07-00001 Other3/7/20073/8/20073/8/2007 9:34:39 AMAPART
conference Eric; Phone #: ###-#### Internet Inspection Request from: Stacie Backus-this was a walk thru with mike from buss, install dbca on building supply, isolate mech rooms with rpba, cap off all open drains, install hvb's on all hosebibs & boiler bibs, install exspantion tank, install rpba or delete hose for ?. label all non potible water, have all devices tested & certifed.