MEC12-00728
| Rough-in | 3/8/2012 | 3/8/2012 | 3/8/2012 1:56:07 PM | P | FAIL |
|
|
Phone #: ###-#### >> Inspection requested via web by Mike Almanza need gas line ran into fireplace
|
MEC12-00703
| Pressure Test | 3/7/2012 | 3/8/2012 | 3/8/2012 1:55:37 PM | P | PASS |
|
|
Pressure test for underground gas line. Inspection to be done late afternoon please. questions, please call Jason Shipp @ ###-#### >> Inspection requested via web by Terisa Rantala ok gas line from house to firepit only
|
MEC12-00140
| Final | 3/8/2012 | 3/8/2012 | 3/8/2012 11:05:45 AM | A | FAIL |
|
|
Please call with any questions or concerns. THank you Phone #: ###-#### >> Inspection requested via web by Jennifer Roy Air balance report is showing wrong design cfm. Need air balance to correct fan speed.
|
MEC12-00139
| Final | 3/8/2012 | 3/8/2012 | 3/8/2012 11:05:10 AM | A | FAIL |
|
|
Please call with any questions or concerns. Thank you Phone #: ###-#### >> Inspection requested via web by Jennifer Roy Air balance report is showing wrong design cfm. Need air balance to correct fan speed.
|
MEC12-00368
| Pressure Test | 3/5/2012 | 3/8/2012 | 3/8/2012 10:59:59 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Lisa Whitney 20#
|
MEC12-00368
| Rough-in | 3/5/2012 | 3/8/2012 | 3/8/2012 10:59:38 AM | A | PASS |
|
|
duct blast 10am Phone #: ###-#### >> Inspection requested via web by Lisa Whitney duct blast ok
|
MEC12-00717
| Final | 3/7/2012 | 3/8/2012 | 3/8/2012 10:34:12 AM | P | CANC |
|
|
INSTALLER CHUCK ###-#### Phone #: ###-#### >> Inspection requested via web by Dustin Rich Inspection cancelled from web by: Dustin Rich
|
MEC12-00557
| Pressure Test | 3/7/2012 | 3/8/2012 | 3/8/2012 10:04:01 AM | A | CANC |
|
|
Building Energy will perform the duct blast test on 3/8/12 at 10am Phone #: ###-#### >> Inspection requested via web by Debbie Marino already approved
|
MEC12-00557
| Rough-in | 3/7/2012 | 3/8/2012 | 3/8/2012 10:03:25 AM | A | CANC |
|
|
Building Energy will perform the duct blast test on 3/8/12 at 10am Phone #: ###-#### >> Inspection requested via web by Debbie Marino already approved
|
MEC12-00658
| Rough-in | 3/8/2012 | 3/8/2012 | 3/8/2012 10:02:53 AM | A | PASS |
|
|
pressure test 20#, duct blast ok
|
MEC12-00707
| Final | 3/6/2012 | 3/8/2012 | 3/8/2012 9:39:13 AM | A | FAIL |
|
|
Call Justin to coordinate time for inspection Phone #: ###-#### >> Inspection requested via web by Tom Soniville need b-vent flue to furnace, water heater pan drain separatly to outside, cannot have overflow condensate terminate at floor
|
MEC12-00687
| Rough-in | 3/7/2012 | 3/8/2012 | 3/8/2012 9:37:09 AM | A | PASS |
|
|
please meet Matt at 9am for duct blaster test. Thanks, Andrea. Phone #: ###-#### x0000 >> Inspection requested via web by Andrea Creek
|