FIR16-00787
| INSP-Sprinkler Rough-in | 3/8/2017 | 3/8/2017 | 3/8/2017 3:26:04 PM | P | PASS |
|
|
Rough to cover inspection for underground supply complete, approved for cover.
|
FIR16-00790
| INSP-Sprinkler Rough-in | 3/8/2017 | 3/8/2017 | 3/8/2017 3:25:41 PM | P | PASS |
|
|
Rough to cover inspection for underground supply complete, approved for cover.
|
FIR16-00786
| INSP-Sprinkler Rough-in | 3/8/2017 | 3/8/2017 | 3/8/2017 3:24:48 PM | P | PASS |
|
|
Rough to cover inspection for underground supply complete, approved for cover.
|
FIR16-00511
| INSP-Sprinkler Rough-in/Hydro | 3/7/2017 | 3/8/2017 | 3/8/2017 2:29:03 PM | P | PART |
|
|
Hydro for overhead fire sprinkler piping on levels 1, 2 and 4 complete, level 3 lost pressure, will need to have hydro test completed again for level 3 after repair is made. Rough to cover inspection /tenting inspection complete, all can be covered with exception to the appartment with the 2 inch CPVC suppling the riser from the standpipe/FDC, no hangers were on the 2 inch at time of inspection.
|
FIR16-00512
| INSP-Supply line flush | 3/7/2017 | 3/8/2017 | 3/8/2017 12:51:00 PM | P | PART |
|
|
Inspection request is for underground rough/hydro, not supply line flush. Underground rough to cover inspection complete, underground hydro complete.
|
FIR16-00511
| INSP-Supply line flush | 3/7/2017 | 3/8/2017 | 3/8/2017 12:50:29 PM | P | PART |
|
|
Inspection request is for underground rough/hydro, not supply line flush. Underground rough to cover inspection complete, underground hydro complete.
|