MEC00-00711
| Rough-in | 3/8/2000 | 3/9/2000 | 3/9/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/08/2000 at 15:04:13. Contact: ###-####.
|
MEC00-00329
| Rough-in | 3/8/2000 | 3/9/2000 | 3/9/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/08/2000 at 15:18:32. Contact: ###-####.
|
MEC00-00023
| Final | 3/8/2000 | 3/9/2000 | 3/9/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/08/2000 at 15:23:35. Contact: ###-####.
|
MEC00-00787
| Final | 3/8/2000 | 3/9/2000 | 3/9/2000 12:00:00 AM | A | FAIL |
|
|
###-#### michael Left C/N & called. 3/9/00 2:20:24 PM
|
MEC00-00797
| Pressure Test | 3/9/2000 | 3/9/2000 | 3/9/2000 12:00:00 AM | P | PASS |
|
|
###-####\\Glad Tidings Church\\install furnace and gas piping
|
MEC00-00195
| Final | 3/8/2000 | 3/9/2000 | 3/9/2000 12:00:00 AM | P | FAIL |
|
|
###-#### michael left cn and called 3/9/00 2:20:24 pm
|
MEC99-02279
| Final | 3/9/2000 | 3/9/2000 | 3/9/2000 12:00:00 AM | P | FAIL |
|
|
No answer.
|
MEC00-00788
| Final | 3/8/2000 | 3/9/2000 | 3/9/2000 12:00:00 AM | P | PASS |
|
|
###-####
|
MEC00-00130
| Final | 3/8/2000 | 3/9/2000 | 3/9/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/08/2000 at 14:15:32. Contact: ###-####.
|