Inspections for the day of: Wednesday, March 9, 2005.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Johnson
TitlePLM-INSPECTOR
Phone #794-9476
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM05-00635 Plumbing Rough-in3/8/20053/9/20053/9/2005 12:00:00 AMAPASS
jeff ###-####
PLM05-00640 Sprinkler (Final)3/9/20053/9/20053/9/2005 12:00:00 AMPPASS
morgan ###-####
PLM05-00537 Plumbing Rough-in3/9/20053/9/20053/9/2005 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 3/9/2005 at 8:44:40 AM. Contact: ###-####.
PLM05-00402 Final3/9/20053/9/20053/9/2005 12:00:00 AMPPASS
bob; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
PLM05-00409 Final3/9/20053/9/20053/9/2005 12:00:00 AMPCANC
Contact Scott with questions.; Phone #: ###-#### Internet Inspection Request from: Roger Patterson canc. by Roger 3/9/2005 1:31:13 PM
PLM05-00641 Sprinkler (Final)3/9/20053/9/20053/9/2005 12:00:00 AMPPASS
bob-- ###-#### - backflow for comom area
PLM05-00645 Sprinkler (Final)3/9/20053/9/20053/9/2005 12:00:00 AMPPART
###-#### - cody tie in ok ok to cover need to have double check certified 3/9/2005 11:35:28 AM
PLM05-00646 Plumbing Rough-in3/9/20053/9/20053/9/2005 12:00:00 AMPPASS
jp simons-- ###-####
PLM04-02609 Final3/8/20053/9/20053/9/2005 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 3/8/2005 at 2:05:06 PM. Contact: ###-####. made walk through of 1st and second floor room,s only 3/9/2005 3:47:09 PM