BLD05-03063
| FIRE-Final Inspection | 3/9/2006 | 3/9/2006 | 3/9/2006 4:52:28 PM | P | FAIL |
|
|
install ceiling tile and provide verification of annual sprinkler inspection
|
BLD04-00944
| FIRE-Conference | 3/8/2006 | 3/9/2006 | 3/9/2006 3:46:11 PM | P | DONE |
|
|
went over life safety comments with contractor
|
FIR06-00103
| INSP-Final Inspection | 3/8/2006 | 3/9/2006 | 3/9/2006 3:29:19 PM | P | PASS |
|
|
Permit finaled
|
FIR06-00074
| INSP-Final Inspection | 3/9/2006 | 3/9/2006 | 3/9/2006 2:36:14 PM | P | PASS |
|
|
permit finaled
|
FIR06-00074
| INSP-Sprinkler Rough-in/Hydro | 3/9/2006 | 3/9/2006 | 3/9/2006 2:35:43 PM | P | PASS |
|
|
permit finaled
|
BLD05-03296
| FIRE-Final Inspection | 3/8/2006 | 3/9/2006 | 3/9/2006 1:45:19 PM | A | FAIL |
|
|
Racks are installed per racking permit review. But overhead sprinkler system needs to be resubmitted due to the rack system. Racking permit can be finaled if nothing changes due to the sprinkler resubmittals. Per Bill Alexander the longitudinal and transverse flue spaces are ok tenativly as installed, again that could change due to the sprinkler resubmittals.
|
FIR05-00771
| INSP-Sprinkler Rough-in/Hydro | 3/8/2006 | 3/9/2006 | 3/9/2006 1:32:25 PM | A | PART |
|
|
200lb. hydro test for the dry system passed. Hydro test for the wet system failed. Also still need the fdc installed and hydro tested.
|
BLD05-03417
| FIRE-Final Inspection | 3/7/2006 | 3/9/2006 | 3/9/2006 12:32:03 PM | A | PASS |
|
|
Life safety finaled
|
FIR05-00845
| INSP-Final Inspection | 3/7/2006 | 3/9/2006 | 3/9/2006 11:43:42 AM | A | PASS |
|
|
Permit finaled
|
BLD05-03192
| FIRE-Final Inspection | 3/7/2006 | 3/9/2006 | 3/9/2006 11:43:07 AM | A | PASS |
|
|
Life safety finaled
|
BLD05-03127
| FIRE-Final Inspection | 3/7/2006 | 3/9/2006 | 3/9/2006 11:42:23 AM | A | PASS |
|
|
Life safety finaled
|
FIR05-00794
| INSP-Final Inspection | 3/7/2006 | 3/9/2006 | 3/9/2006 11:41:51 AM | A | PASS |
|
|
Permit finaled
|
FIR06-00095
| INSP-Final Inspection | 3/7/2006 | 3/9/2006 | 3/9/2006 11:41:24 AM | A | PASS |
|
|
Permit finaled
|
FIR06-00121
| INSP-Final Inspection | 3/8/2006 | 3/9/2006 | 3/9/2006 8:37:47 AM | A | PASS |
|
|
Permit finaled
|
FIR06-00040
| INSP-Final Inspection | 3/8/2006 | 3/9/2006 | 3/9/2006 8:06:14 AM | A | FAIL |
|
|
no access to part of the job and ceiling tile and canopies are missing
|