Inspections for the day of: Friday, March 9, 2007.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR06-00958 INSP-Sprinkler Rough-in/Hydro3/8/20073/9/20073/9/2007 5:03:30 PMPPASS
Above ground hydro test of the first and second floors of building A have passed. The first floor of building A is ok to cover.
FIR06-00881 INSP-Final Inspection3/9/20073/9/20073/9/2007 4:18:49 PMPFAIL
Inspection was for rough to cover and was not ready for a final. Sprinkler piping is ok to cover.
FIR07-00114 INSP-Final Inspection3/8/20073/9/20073/9/2007 4:17:22 PMPPASS
permit finaled
FIR07-00133 INSP-Final Inspection3/8/20073/9/20073/9/2007 2:46:16 PMAPASS
permit finaled
MIS06-00244 FIR-Final3/8/20073/9/20073/9/2007 1:06:24 PMAPASS
life safety passed.
BLD06-02378 FIRE-Final Inspection3/8/20073/9/20073/9/2007 11:26:29 AMAPASS
life safety passed
BLD06-02379 FIRE-Final Inspection3/8/20073/9/20073/9/2007 11:26:04 AMAPASS
life safety passed.
BLD06-01729 FIRE-Final Inspection3/8/20073/9/20073/9/2007 11:25:35 AMAPASS
Life safety passed.
FIR06-00624 INSP-Final Inspection3/8/20073/9/20073/9/2007 9:31:40 AMAPASS
permit finaled
BLD07-00309 FIRE-Final Inspection3/8/20073/9/20073/9/2007 8:41:44 AMAFAIL
Several pendant sprinkler heads are too close to one another and are overspaced off of the east wall. A separate permit will be required for this work.