Inspections for the day of: Monday, March 9, 2009.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR06-00108 FIR-Aging Inspection3/9/20093/9/20093/9/2009 4:23:03 PMPNR
I spoke to jeff and he stated that he would follow up on the status of the project and get back to me.
FIR00-00501 INSP-Conference3/9/20093/9/20093/9/2009 4:22:10 PMPDONE
I spoke to keith about the need to get this permit inspected and finaled. He stated that he would follow up.
FIR08-00675 INSP-Sprinkler Rough-in3/9/20093/9/20093/9/2009 2:30:19 PMPPASS
The sprinkler piping above the ceiling in the third floor central stair tower is ok to cover.
FIR08-00675 INSP-Supply line flush3/4/20093/9/20093/9/2009 2:28:23 PMPPASS
The underground flush passed.
BLD08-01439 FIRE-Final Inspection3/6/20093/9/20093/9/2009 2:27:39 PMAFAIL
Contractor was not available for the inspection and there was no access to inside of the building.