ESC10-00135
| Site Preparation | 3/9/2010 | 3/9/2010 | 3/15/2010 2:09:31 PM | P | CANC |
|
|
Mike:
|
ESC09-00812
| Conference | 3/9/2010 | 3/9/2010 | 3/9/2010 9:48:43 AM | A | DONE |
|
|
Met with J. Gilliland and P. Woods for general discussion of project: Discussions resulted in agreements: 1) Pond number one should be protected from sediment; 2) De-watering trench should be lined, inspected and repairs made if necessary, 3) Sample results for discharge if above background at Sand Creek will require additional steps to achieve compliance. Jenifer and Paul will attend the Friday meeting at the Train Depot with Steve W.
|