FIR07-00745
| INSP-Conference | 3/26/2009 | 3/27/2009 | | P | |
|
|
Inspection follow up.
|
FIR09-00187
| INSP-Final Inspection | 3/31/2009 | 4/1/2009 | 4/1/2009 3:27:45 PM | P | FAIL |
|
|
I stopped at the project twice but the fire alarm interconnection was not complete either time. It will need to be rescheduled.
|
BLD09-00277
| FIRE-Final Inspection | 3/31/2009 | 4/1/2009 | 4/1/2009 3:26:24 PM | A | FAIL |
|
|
The new wall has caused the existing sprinkler pendants to be overspaced and a separate permit is required for this work. All other life safety items are ok to pass when this fire sprinkler work is complete.
|
BLD09-00098
| FIRE-Final Inspection | 4/1/2009 | 4/1/2009 | 4/1/2009 3:25:11 PM | P | PASS |
|
|
Life safety passed.
|
FIR09-00145
| INSP-Final Inspection | 4/1/2009 | 4/1/2009 | 4/1/2009 3:24:39 PM | P | PASS |
|
|
Permit finaled
|
BLD09-00380
| FIRE-Final Inspection | 3/31/2009 | 4/1/2009 | 4/1/2009 12:47:19 PM | A | FAIL |
|
|
Provide the suite number at the front door, remove the thumbturn deadbolts from both exterior exit doors and provide approved single action hardware (lever) and provide current inspection tag for the fire extinguisher. Only one extinguisher is needed.
|
BLD08-01664
| FIRE-Final Inspection | 3/31/2009 | 4/1/2009 | 4/1/2009 12:30:13 PM | A | PART |
|
|
A temporary occupancy was given with mark senteno's permission until the fire alarm permit is finaled. The temporary is only until April 19th as agreed upon with Stock Construction.
|
FIR09-00130
| INSP-Final Inspection | 3/31/2009 | 4/1/2009 | 4/1/2009 12:24:38 PM | A | PART |
|
|
A temporary occupancy was given until the interconnect with the suppression system is tested/inspected and shown on as-built drawings. Also need the elevator recall functions tested inspected. A temporary was approved by mark senteno.
|
BLD08-01467
| FIRE-Final Inspection | 3/31/2009 | 4/1/2009 | 4/1/2009 11:33:25 AM | A | FAIL |
|
|
The new emergency lighting located in the southwest exit corridor did not function. The project related fire alarm permit needs to be finaled.
|
FIR08-00607
| INSP-Final Inspection | 3/31/2009 | 4/1/2009 | 4/1/2009 11:32:17 AM | A | FAIL |
|
|
The spacing of the strobes has been corrected but functionality was not tested. None of the duct smoke detectors tested shutdown upon detection of smoke. The correct orfices need to be installed in both of the fire sprinkler inspector test lines. The flow switch on the east system did not operate. The west sprinkler system flow switch was not tested. The outside alarm bell did not operate on the east sprinkler system. The sprinkler tamper switches did operate correctly.
|
BLD09-00062
| FIRE-Final Inspection | 3/31/2009 | 4/1/2009 | 4/1/2009 10:04:52 AM | A | PART |
|
|
The six office/meeting rooms are ok to occupy. The project related fire alarm permit needs to be finaled and the ceiling tile to the north west of these six new rooms needs to be installed.
|
BLD09-00062
| FIRE-Alarm Testing | 3/31/2009 | 4/1/2009 | 4/1/2009 9:55:55 AM | A | DONE |
|
|
See the project related fire alarm permit for the items needing addressed.
|
FIR09-00185
| INSP-Final Inspection | 3/31/2009 | 4/1/2009 | 4/1/2009 9:55:06 AM | A | PASS |
|
|
Permit finaled
|
FIR09-00061
| INSP-Alarm Testing | 3/31/2009 | 4/1/2009 | 4/1/2009 9:54:27 AM | A | PART |
|
|
The notification devices operated in the six new office/meeting rooms. Plan resubmittals are required due to another area to the south, sheet 5 of 5, where work has not been performed. Per the personell on site this work is not going to be performed which changes the scope of work for the fire alarm permit thus the reason for the resubmittal. The other reason is instead of 15cd strobes being installed in the six rooms 30cd strobes have been installed which changes the battery and EOL calculations.
|