FIR13-00114
| INSP-Sprinkler Rough-in/Hydro | 4/1/2013 | 4/1/2013 | 4/1/2013 5:04:44 PM | P | PART |
|
|
West conference room okay for cover.
|
FIR13-00146
| INSP-Sprinkler Rough-in | 4/1/2013 | 4/1/2013 | 4/1/2013 5:02:16 PM | P | PART |
|
|
Okay to cover new sprinkler piping at the restroom addition.
|
BLD12-02258
| FIRE-Conference | 4/1/2013 | 4/1/2013 | 4/1/2013 4:59:20 PM | P | DONE |
|
|
|
FIR13-00089
| INSP-Final Inspection | 4/1/2013 | 4/1/2013 | 4/1/2013 4:58:07 PM | P | PASS |
|
|
Scope of work completed. Permit final okay after system is charged.
|
FIR11-00458
| FIR-Aging Inspection | 4/1/2013 | 4/1/2013 | 4/1/2013 12:23:59 PM | | PEND |
|
|
Pending site inspection request
|
BLD13-00242
| FIRE-Sprinkler Rough-in | 4/1/2013 | 4/1/2013 | 4/1/2013 12:20:32 PM | A | PART |
|
|
Okay to cover overhead fire sprinkler modifications at the new ceiling. Discussed existing fire alarm system and remodel work.
|
BLD13-00212
| FIRE-Final Inspection | 3/31/2013 | 4/1/2013 | 4/1/2013 12:16:09 PM | A | DONE |
|
|
13th floor fire life safety passed walkthrough. NOTE: fire extinguishers are due annual certification this month.
|
FIR12-00745
| INSP-Sprinkler Rough-in | 4/1/2013 | 4/1/2013 | 4/1/2013 12:12:02 PM | A | PART |
|
|
Overhead fire sprinkler work at the grid ceilings is approved for cover- ref. dated notes on plans.
|