ESC09-00352
| General Inspection | 4/1/2014 | 4/1/2014 | 4/1/2014 4:19:06 PM | | PASS |
|
|
No new activity or changes.
|
ESC13-00283
| Aging Inspection | 4/1/2014 | 4/1/2014 | 4/1/2014 3:42:41 PM | | PASS |
|
|
Landscaping in progress. No work today during the rain. Next inspection it should be stabilized. No violations observed.
|
ESC13-00997
| General Inspection | 4/1/2014 | 4/1/2014 | 4/1/2014 2:59:15 PM | | PASS |
|
|
|
ESC13-00277
| General Inspection | 4/1/2014 | 4/1/2014 | 4/1/2014 2:49:28 PM | | PASS |
|
|
WIP. No sediment leaving site. No MS4 in area
|
ESC13-00447
| Aging Inspection | 4/1/2014 | 4/1/2014 | 4/1/2014 2:02:34 PM | | PASS |
|
|
Addition in progress. No corrections at this time. Permit posted.
|
ESC13-00939
| General Inspection | 4/1/2014 | 4/1/2014 | 4/1/2014 1:57:16 PM | P | PASS |
|
|
Construction appears to be complete. Some materials still on site. No corrections at this time, will check for Site Final next inspection.
|
ESC13-00915
| General Inspection | 4/1/2014 | 4/1/2014 | 4/1/2014 1:56:04 PM | | PASS |
|
|
Finaled.
|
ESC13-00915
| DOC - Permit Finaled | 4/1/2014 | 4/1/2014 | 4/1/2014 1:55:43 PM | P | PASS |
|
|
Grading and utility work is complete. Parking lot has been cleaned. Some materials still on site for vertical construction project. Covered under ESC13-00939. Conditions satisfied for this permit.
|
ESC13-00161
| Aging Inspection | 4/1/2014 | 4/1/2014 | 4/1/2014 1:22:20 PM | | PASS |
|
|
Finaled.
|
ESC13-00161
| DOC - Permit Finaled | 4/1/2014 | 4/1/2014 | 4/1/2014 1:22:02 PM | P | PASS |
|
|
Construction is complete. Driveway returned to pre-existing gravel conditions. No further ESC inspections necessary.
|
ESC13-00130
| Aging Inspection | 4/1/2014 | 4/1/2014 | 4/1/2014 1:20:35 PM | | PASS |
|
|
Project is not yet complete. Permit posted. No stockpiles or activity adjacent to ditch. No corrections required.
|
ESC13-00193
| Conference | 3/31/2014 | 4/1/2014 | 4/1/2014 9:26:20 AM | P | CANC |
|
|
Conference with Wright construction to confirm that the SWO on site can be lifted and construction can resume. Re-inspection fee already paid.
Tentatively re-scheduled due to rain
|