ESC15-00094
| General Inspection | 4/1/2015 | 4/1/2015 | 4/2/2015 2:38:25 PM | P | PART |
|
|
WIP on grading future roadway area in Boulder Heights #6. Upper access points are blocked off to prevent unauthorized access and prevent trackout. No dust; work staying within limits of disturbance.
Corrections to be completed by next week:
1. Install check dams in along the construction entrance where runoff channels down. 2. Install new heavy duty rock construction entrance 3. Install sediment basin or other BMP for sediment control for upper disturbed slope runoff occuring above the stormwater pond.
Will check back next week. Verbal corrections given to RP.
|
ESC14-00381
| General Inspection | 4/1/2015 | 4/1/2015 | 4/1/2015 2:01:51 PM | | PASS |
|
|
Stockpile area for BH#5 is now the location of grading and utility installed for BH#6 and is covered and inspected under ESC15-00094. No corrections at site required at this time.
|
ESC14-00381
| DOC - Permit Finaled | 4/1/2015 | 4/1/2015 | 4/1/2015 2:00:20 PM | P | PASS |
|
|
|
ESC14-00078
| Aging Inspection | 4/1/2015 | 4/1/2015 | 4/1/2015 12:13:51 PM | | PASS |
|
|
No construction at East Boise baseball complex. Permit still valid; no issues.
|
ESC15-00239
| Site Preparation | 3/31/2015 | 4/1/2015 | 4/1/2015 11:59:56 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Austin Wagner
Permit posted. BMPs in place. Approved.
|
ESC14-00846
| DOC - Permit Finaled | 4/1/2015 | 4/1/2015 | 4/1/2015 11:57:49 AM | P | PASS |
|
|
Townhome compete. No further ESC inspections required for this permit. Tripplet sub currently in compliance. No trackout, discharges, uncontained trash.
|
ESC14-00844
| DOC - Permit Finaled | 4/1/2015 | 4/1/2015 | 4/1/2015 11:57:07 AM | P | PASS |
|
|
Townhome compete. No further ESC inspections required for this permit. Tripplet sub currently in compliance. No trackout, discharges, uncontained trash.
|
ESC14-00804
| General Inspection | 4/1/2015 | 4/1/2015 | 4/1/2015 11:54:19 AM | | PASS |
|
|
Triplett townhome construction complete. Not yet landscaped but sediment is staying onsite and RP is requiring regular housekeeping/sweeping. Active homes adjacent to site with open ESC permits.
|
ESC14-00804
| DOC - Permit Finaled | 4/1/2015 | 4/1/2015 | 4/1/2015 11:52:33 AM | P | PASS |
|
|
|
ESC14-00818
| General Inspection | 4/1/2015 | 4/1/2015 | 4/1/2015 11:47:12 AM | | PASS |
|
|
No activity or violations at site. Currently project on hold and is graded with utilities installed for further vertical construction.
|
ESC13-01279
| General Inspection | 4/1/2015 | 4/1/2015 | 4/1/2015 11:40:08 AM | | PASS |
|
|
Lucky Harris/Harris Crossing sub has townhomes in progress. Trash and materials are contained, perimeter BMPs are installed, DI protection provided, and employees are staying off open areas to prevent disturbance/trackout. Designated and lined washout is being utilized and has remaining capacity. Landscaping crews on site working to vegetate/stabilize subdivision perimter.
No corrections at this time.
|
ESC13-01058
| DOC - Permit Finaled | 4/1/2015 | 4/1/2015 | 4/1/2015 11:13:24 AM | P | PASS |
|
|
Washington Federal TI WIP. Work to be covered under ESC14-01116. No further inspections required on this permit.
|
ESC14-01116
| Conference | 3/31/2015 | 4/1/2015 | 4/1/2015 11:10:49 AM | A | PASS |
|
|
John Phone #: ###-####
Work in drive thru lane to expand air exhaust vault. Two conctret slabs will be removed as well as dirt. Dirt will be stockpiled in drivethru lane that is contained and will place a sand bag on the drainage cut through on the curb. Receiving drop inlet has sediment filter bag already installed.
Stockpile will be stored on tarp and also covered as necessary.
Approved to continue. Very clean site.
|
ESC14-00892
| Aging Inspection | 4/1/2015 | 4/1/2015 | 4/1/2015 10:42:48 AM | | PASS |
|
|
Townhome subdivision access road, utilities, and stormwater drainage system have been completed. Malad street is free of trackout and sediment in gutter.
No vertical construction has started yet. Once it starts, drop inlet protection should be provided on the private storm drain at south end of site.
No issues, no sediment runoff or fugitive dust..
|
ESC14-00486
| General Inspection | 4/1/2015 | 4/1/2015 | 4/1/2015 9:48:46 AM | | PASS |
|
|
WIP. No trackout of discharges/spills observed. Work confined within curbed area. Drop inlets have sediment protection. Approved
|
ESC14-00565
| Aging Inspection | 4/1/2015 | 4/1/2015 | 4/1/2015 9:02:24 AM | | PASS |
|
|
Construction complete. Disturbed areas landscaped and hard surfaces have been swept to remove loose dirt for construction. ESC permit finaled.
|
ESC14-00565
| DOC - Permit Finaled | 4/1/2015 | 4/1/2015 | 4/1/2015 9:01:40 AM | P | PASS |
|
|
|
ESC14-00449
| General Inspection | 4/1/2015 | 4/1/2015 | 4/1/2015 8:08:09 AM | | CANC |
|
|
Bristlewood already inspected 3/30, 3/31. No Street sweeping requested 3/31. Followup inspection to occur later in week.
|