ELE15-00495
| Electrical Rough-In | 4/1/2016 | 4/1/2016 | 4/1/2016 4:06:11 PM | P | PASS |
|
|
Cover inspections for walls Phone #: ###-#### Inspection requested via web by Toby Groves Rough-in ok cover interior walls highlighted in green and dated
|
ELE16-00303
| Electrical Rough-In | 4/1/2016 | 4/1/2016 | 4/1/2016 4:05:18 PM | P | PASS |
|
|
Cover inspections for walls Phone #: ###-#### Inspection requested via web by Toby Groves Rough-in ok cover interior walls highlighted green and dated
|
ELE16-00506
| Electrical Rough-In | 4/1/2016 | 4/1/2016 | 4/1/2016 3:02:35 PM | P | PASS |
|
|
We are requesting an underground inspection for the northwest area for this afternoon. Our contacts are Bobbie @ ###-#### or Tony @ ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate rough-in ok cover UL Listed floor boxes and N.W. corner underground.
|
ELE16-00662
| Electrical Rough-In | 3/31/2016 | 4/1/2016 | 4/1/2016 1:43:25 PM | A | PASS |
|
|
Site lighting underground north and west of main bldg. Phone #: ###-#### Inspection requested via web by Debby Pierce rough-in ok cover underground,Prefab pole bases not on site.
|
ELE16-00205
| Electrical Rough-In | 3/31/2016 | 4/1/2016 | 4/1/2016 11:31:40 AM | A | PASS |
|
|
underground; Phone #: ###-#### rougjh-in ok pour as sign and dated on plans
|
ELE16-00155
| Electrical Rough-In | 4/1/2016 | 4/1/2016 | 4/1/2016 10:23:47 AM | A | PASS |
|
|
Contact: Mike Ennis - underground inspection please Phone #: ###-#### Inspection requested via web by Deb Gooden rough-in ok cover u/g listed floor boxes as per highlighted dated on plans
|
ELE16-01009
| Final | 4/1/2016 | 4/1/2016 | 4/1/2016 10:05:56 AM | A | NR |
|
|
Phone #: ###-#### Inspection requested via web by Neal Rumsey no ready for final at this time
|
ELE16-01009
| Rough-In Permanent Service | 4/1/2016 | 4/1/2016 | 4/1/2016 9:47:10 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Neal Rumsey No cover for exterior /soffits no fire chalk rough-in interior only p/s u/g n ok
|