Inspections for the day of: Monday, April 1, 2019.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMark Moncarr
TitleELE-INSPECTOR
Phone #685-9023
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE17-00150 ELE-Aging Inspection4/1/20194/1/20194/2/2019 12:24:37 PM PASS
Another contractor took job over and at was finaled.
ELE18-04396 Electrical Rough-In4/1/20194/1/20194/1/2019 3:10:38 PMPPASS
Contact is Josh Smith Phone #: ###-#### Inspection requested via web by Candy Magly Ok cover kitch, living and mstr addition. Asked electrician to verify sink size in mstr bath so recept is within 3ft.
ELE18-03142 Final4/1/20194/1/20194/1/2019 2:50:54 PMPPASS
Code is DAM Ok final.
ELE19-01108 Rough-In Permanent Service3/31/20194/1/20194/1/2019 2:35:40 PMPPASS
The meter and service panel are being moved because the existing mast location is within the new addition on the back of the house, and must be moved to the outside of the new addition in order to get trusses up. The intention is get power reconnected by the end of the day, but we won''t be ready for an inspection until near the end of the day. If you call/text after noon I should be able to provide an estimated time we''ll be ready for the inspection. Phone #: ###-#### Inspection requested via web by Dan Hilke p/s o/h n ok
ELE18-01606 Electrical Rough-In3/29/20194/1/20194/1/2019 2:10:36 PMPPASS
Building B, C-Units 3rd ; 4th floors rough in inspection.
Building B, 1st floor grid inspection D-Units.
Phone #: ###-#### Inspection requested via web by James Kemner Ok cover 1st flr, D units ceilings, 3rd flr, C units, and 1st flr, C corridor.
ELE18-01329 Electrical Rough-In3/29/20194/1/20194/1/2019 1:25:45 PMAPASS
This request is for a driveway heat inspection Phone #: ###-#### Inspection requested via web by Darryn Coburn Ok cover.
ELE19-01120 Permanent Service4/1/20194/1/20194/1/2019 12:43:41 PMPPASS
Phone #: ###-#### Inspection requested via web by Jim Williams p/s u/g rec ok
ELE19-01104 Conference3/31/20194/1/20194/1/2019 10:04:21 AMADONE
I Want To Walk Through This House I Have Some Questions And Concerns With The Way It Stands Now! Allot Of Work Done And Allot Of Red Flags! Dave Phone #: ###-#### Inspection requested via web by jason shifflett Walked through home with Dave. Numerous areas need addressed. Another person wired home. No past electrical permits were pulled. Mast height needs changed.
ELE19-01084 Electrical Rough-In3/29/20194/1/20194/1/2019 9:46:57 AMAPASS
Please call Kevin ###-#### to make sure there is someone home. If you have any questions please feel free to contact Andrew ###-####. Thanks!! Phone #: ###-#### Inspection requested via web by Clayton Morgan Ok cover kitchen.
ELE19-01097 Temporary Service3/29/20194/1/20194/1/2019 9:22:41 AMAPASS
If you have any questions please feel free to contact Luke ###-####. Thanks!!! Phone #: ###-#### Inspection requested via web by Clayton Morgan t/s u/g n ok
ELE19-01070 Final3/29/20194/1/20194/1/2019 9:22:17 AMAPASS
There will be people there. If you have any questions please feel free to contact Fred ###-####. Thanks!!! Phone #: ###-#### Inspection requested via web by Clayton Morgan Ok final. 30a, lockout.
ELE19-01069 Final3/29/20194/1/20194/1/2019 9:21:53 AMAPASS
There will be people there. If you have any questions please feel free to contact Fred ###-####. Thanks!!! Phone #: ###-#### Inspection requested via web by Clayton Morgan Ok final.30a, panel within sight.
ELE16-04136 ELE-Request for Extension3/29/20194/1/20194/1/2019 6:00:33 AMAPASS
Phone #: ###-#### Inspection requested via web by Same Electric Extension OK. Job is still in progress.
ELE18-01329 Electrical Rough-In3/29/20194/1/20193/29/2019 4:37:52 PMACANC
this request is for a driveway heat inspection. Thank you! Phone #: ###-#### >> Inspection requested via web by Darryn Coburn Inspection cancelled from web by: Darryn Coburn