MEC98-01063
| INSP - Final | 4/9/1998 | 4/10/1998 | 4/10/1998 12:00:00 AM | A | FAIL |
|
|
need to protect the exposed flue pipe and gas pipe, told them to recall inspection.
|
MEC98-01063
| INSP - Final | 4/9/1998 | 4/10/1998 | 4/10/1998 12:00:00 AM | A | FAIL |
|
|
need to protect the exposed flue pipe and gas pipe, told them to recall inspection.
|
MEC98-01128
| INSP - Framing/ Rough-in | 4/9/1998 | 4/10/1998 | 4/10/1998 12:00:00 AM | A | PART |
|
|
gas test ok .left note to recall inspection at same time as framing not yet finished
|
BLD98-00459
| INSP - Foundation | 4/9/1998 | 4/10/1998 | 4/10/1998 12:00:00 AM | A | NR |
|
|
ready for a pm insp.
|
BLD98-00866
| INSP - Foundation | 4/9/1998 | 4/10/1998 | 4/10/1998 12:00:00 AM | A | PART |
|
|
footing have been poured prior to inspection. Walls are not yet poured and are per the plan,also set backs are ok.
|
BLD98-00463
| INSP - Foundation | 4/9/1998 | 4/10/1998 | 4/10/1998 12:00:00 AM | P | PASS |
|
|
Scheduled by Hello!.
|
BLD97-03129
| INSP - Framing/Rough-in | 4/10/1998 | 4/10/1998 | 4/10/1998 12:00:00 AM | P | CANC |
|
|
done by 301.
|
BLD98-00459
| INSP - Foundation | 4/9/1998 | 4/10/1998 | 4/10/1998 12:00:00 AM | P | PASS |
|
|
Scheduled by Hello!. Contact phone is [3714830].
|