Inspections for the day of: Tuesday, April 10, 2001.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Johnson
TitlePLM-INSPECTOR
Phone #794-9476
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM01-01045 Sprinkler (Final)4/9/20014/10/20014/10/2001 12:00:00 AMAPASS
Douglas ###-####
PLM01-01055 Water and/or Sewer4/9/20014/10/20014/10/2001 12:00:00 AMAFAIL
drew ###-#### w/s final need to change one inch building supply line to inch -one quarter. need approved materials where water and sewer cross.need to test both water and sewer lines.cleanouts to be installed in direction of flow need approved transition from pvc to abs pipe. 4/10/2001 11:29:41 AM
PLM00-03311 Final4/10/20014/10/20014/10/2001 12:00:00 AMPCANC
Scott ###-#### late as possible plumbing contractot called and canc. 4/10/2001 2:18:16 PM
PLM01-00278 Final4/10/20014/10/20014/10/2001 12:00:00 AMPPASS
Lee ###-####
PLM01-00967 Plumbing Rough-in4/10/20014/10/20014/10/2001 12:00:00 AMPPASS
Rob ###-#### need to add three fixtures to permit for additional upstairsbath room. 4/10/2001 2:16:12 PM
PLM01-01068 Sprinkler (Final)4/10/20014/10/20014/10/2001 12:00:00 AMPPASS
###-####
PLM01-01069 Sprinkler (Final)4/10/20014/10/20014/10/2001 12:00:00 AMPPASS
###-####
PLM01-01033 Groundwork4/10/20014/10/20014/10/2001 12:00:00 AMPPASS
Scheduled by Inspector: 360 On 4/10/2001 12:18:42 PM
PLM01-01034 Groundwork4/10/20014/10/20014/10/2001 12:00:00 AMPPASS
Scheduled by Inspector: 360 On 4/10/2001 12:20:10 PM