Inspections for the day of: Wednesday, April 10, 2002.
Number of inspections: 20
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorLee Rice
TitlePLM-CHIEF INSPECTOR
Phone #794-9486
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM02-00907 Sprinkler (Final)4/9/20024/10/20024/10/2002 12:00:00 AMAPASS
###-#### carol notified to put gravel under dcva,s. 4/10/2002 11:48:42 AM
PLM02-00916 Water and/or Sewer4/9/20024/10/20024/10/2002 12:00:00 AMAFAIL
jim- ###-#### swr & water pipe 4/10/2002 10:58:54 AM pipe embedded in concrete and no test on. 4/10/2002 11:01:47 AM
PLM02-00916 Water and/or Sewer4/9/20024/10/20024/10/2002 12:00:00 AMAFAIL
jim- ###-#### swr & water pipe 4/10/2002 10:58:54 AM pipe embedded in concrete and no test on. 4/10/2002 11:01:47 AM
PLM02-00462 Final4/9/20024/10/20024/10/2002 12:00:00 AMAFAIL
dave ###-#### fn no access, no body home 4/10/2002 11:38:05 AM
PLM02-00601 Final4/9/20024/10/20024/10/2002 12:00:00 AMAFAIL
ben ###-#### need to lenghen prv line off of water heater 4/10/2002 12:09:21 PM
PLM02-00248 Final4/9/20024/10/20024/10/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 04/09/2002 at 14:25:58. Contact: ###-####. access 8941 on garage
PLM02-00918 Water and/or Sewer4/9/20024/10/20024/10/2002 12:00:00 AMAPASS
###-#### JAN SEWER ONLY
PLM02-00918 Water and/or Sewer4/9/20024/10/20024/10/2002 12:00:00 AMAPASS
###-#### JAN SEWER ONLY
PLM02-00349 Roof Drains4/9/20024/10/20024/10/2002 12:00:00 AMAFAIL
###-#### jerry change fittings to directional for drainage. 4/10/2002 10:02:03 AM
PLM02-00916 Water and/or Sewer4/9/20024/10/20024/10/2002 12:00:00 AMAFAIL
jim- ###-#### swr & water pipe 4/10/2002 10:58:54 AM pipe embedded in concrete and no test on. 4/10/2002 11:01:47 AM
PLM02-00918 Water and/or Sewer4/9/20024/10/20024/10/2002 12:00:00 AMAPASS
###-#### JAN SEWER ONLY
PLM02-00528 Final4/10/20024/10/20024/10/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 04/10/2002 at 07:19:41. Contact: ###-####.
PLM02-00385 Final4/10/20024/10/20024/10/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 04/10/2002 at 07:26:16. Contact: ###-####.
PLM01-04117 Final4/10/20024/10/20024/10/2002 12:00:00 AMPPASS
###-#### rod
PLM02-00901 Plumbing Rough-in4/10/20024/10/20024/10/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 04/10/2002 at 07:40:21. Contact: ###-####.
PLM02-00921 Water and/or Sewer4/10/20024/10/20024/10/2002 12:00:00 AMPPASS
water line ###-#### ray, waterline ok. 4/10/2002 2:53:54 PM
PLM02-00339 Plumbing Rough-in4/10/20024/10/20024/10/2002 12:00:00 AMPPASS
MIKE ###-####
PLM02-00349 Water and/or Sewer4/10/20024/10/20024/10/2002 12:00:00 AMPPASS
Scheduled by Inspector: 309 On 4/10/2002 10:02:24 AM
PLM02-00921 Sprinkler (Final)4/10/20024/10/20024/10/2002 12:00:00 AMPPART
###-#### tie in ok, will call back when backflow valve certified. 4/10/2002 2:53:39 PM
PLM02-00913 Plumbing Rough-in4/10/20024/10/20024/10/2002 12:00:00 AMPPASS
###-####