BLD06-00084
| FIRE-Final Inspection | 4/10/2006 | 4/10/2006 | 4/10/2006 6:37:25 PM | P | FAIL |
|
|
Max occupant load sign is not yet posted, approved plans and sign off card not available on site.
|
FIR05-00875
| INSP-Final Inspection | 4/7/2006 | 4/10/2006 | 4/10/2006 4:55:42 PM | P | FAIL |
|
|
Heads at two locations as marked on approved plans are blocked by surface mounted light obstructions, the elevator shaft has been deleted and divided to form two separate rooms which will require protection per NFPA 13D, witnessed satisfactory UG flush, missing canopy installed while on site.
|
FIR06-00075
| INSP-Sprinkler Rough-in | 4/10/2006 | 4/10/2006 | 4/10/2006 4:00:39 PM | P | DEFR |
|
|
todd; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles No time available for this inspection today, to be rescheduled per conversation with contractor.
|
FIR05-00449
| INSP-Alarm Testing | 4/7/2006 | 4/10/2006 | 4/10/2006 3:59:07 PM | A | PART |
|
|
Tested detection and notification devices on the 3rd and 4th floors, HVAC units were not in a condition to be tested in the fan rooms, missing mag door holder at the 3rd floor north double doors (door release not verified), checked audibility in the fan room on 2nd floor, previous c/n items are satisfactory, discussed inspection schedule for the remainder of this project with D. Maxwell.
|
FIR05-00564
| INSP-Final Inspection | 4/7/2006 | 4/10/2006 | 4/10/2006 2:20:10 PM | P | PASS |
|
|
Verified occupancy use in office 102 does not require visual notification, resubmitted plans verified, permit finaled.
|
BLD04-00949
| FIRE-Final Inspection | 4/10/2006 | 4/10/2006 | 4/10/2006 2:13:08 PM | P | FAIL |
|
|
The project related fire alarm and sprinkler permits must be inspected and approved prior to building life safety final inspection.
|
FIR05-00853
| INSP-Final Inspection | 4/6/2006 | 4/10/2006 | 4/10/2006 2:11:17 PM | P | PASS |
|
|
Items on correction notice have been completed as required, fire sprinkler finaled.
|
FIR05-00586
| INSP-Sprinkler Rough-in/Hydro | 4/10/2006 | 4/10/2006 | 4/10/2006 12:03:36 PM | P | NR |
|
|
Per phone conversation with contractor, project is not ready for a hydrostatic test at this time as scheduled.
|
FIR06-00038
| INSP-Final Inspection | 4/7/2006 | 4/10/2006 | 4/10/2006 11:54:28 AM | A | PASS |
|
|
Fire sprinkler work is satisfactory, permit finaled.
|
FIR06-00183
| INSP-Final Inspection | 4/7/2006 | 4/10/2006 | 4/10/2006 11:52:47 AM | A | PASS |
|
|
Corrections have been made, modifications tested, signals verified, fire alarm inspection passed.
|
FIR06-00083
| INSP-Final Inspection | 4/10/2006 | 4/10/2006 | 4/10/2006 11:33:20 AM | P | PASS |
|
|
Inspection completed in the AM as previously agreed, fire alarm functioned properly, inspection passed.
|
FIR05-00425
| INSP-Sprinkler Rough-in/Hydro | 4/7/2006 | 4/10/2006 | 4/10/2006 11:03:57 AM | A | PART |
|
|
Overhead rough-in inspection for the 6th floor is good for cover at the hard lid areas as discussed, items addressed include missing 4-way EQ brace, blocked ssu at south stair #1, fire caulking not complete in some areas, added lines in guest room soffits must be shown on plan, be aware of possible light fixture and soffit obstructions, some SW heads are not cut in at this time, laundry chute head is not piped.
|
BLD02-02815
| FIRE-Final Inspection | 4/7/2006 | 4/10/2006 | 4/10/2006 10:11:28 AM | A | PASS |
|
|
Outstanding items have been completed, fire life safety inspection passed.
|
FIR06-00128
| INSP-Sprinkler Rough-in/Hydro | 4/7/2006 | 4/10/2006 | 4/10/2006 9:47:20 AM | A | PART |
|
|
Overhead rough-in is good for cover at the four restrooms with hard lids on the first floor as marked on plans, no other areas requested for inspection at this time.
|
FIR05-00804
| INSP-Final Inspection | 4/7/2006 | 4/10/2006 | 4/10/2006 8:20:44 AM | A | CANC |
|
|
we are now ready. Could you please call me when you have an approximate time you'll be out. Thanks, Harry ; Phone #: ###-#### Internet Inspection Request from: Harry Thompson Inspection cancelled from web by: Harry Thompson
|