FIR12-00427
| INSP-Sprinkler Rough-in | 4/9/2013 | 4/10/2013 | 4/10/2013 3:53:33 PM | P | PASS |
|
|
Upper level ceiling tile is ok to cover pipe. Work is being done outside of the scope of work shown on the drawings and will need to be submitted for review. It is protection in a small storage area.
|
FIR12-00695
| INSP-Sprinkler Rough-in | 4/10/2013 | 4/10/2013 | 4/10/2013 3:29:30 PM | P | PASS |
|
|
See the city approved plans for location marked in red where the sprinkler piping can be covered.
|
FIR13-00135
| INSP-Sprinkler Rough-in | 4/10/2013 | 4/10/2013 | 4/10/2013 3:28:28 PM | P | PASS |
|
|
See the city approved plans for areas in phase 1 where the sprinkler piping can be covered.
|
FIR13-00074
| INSP-Sprinkler Rough-in | 4/10/2013 | 4/10/2013 | 4/10/2013 3:26:59 PM | P | PASS |
|
|
Previous correction items on second floor are now corrected and one soffit on the first floor is ok to cover. See red lines on city approved plans.
|
BLD12-00681
| FIRE-Final Inspection | 4/10/2013 | 4/10/2013 | 4/10/2013 3:14:48 PM | P | PASS |
|
|
Life safety passed. Smoke alarms tested.
|
FIR12-00621
| INSP-Final Inspection | 4/10/2013 | 4/10/2013 | 4/10/2013 3:13:32 PM | P | PASS |
|
|
permit finaled
|
FIR12-00622
| INSP-Final Inspection | 4/10/2013 | 4/10/2013 | 4/10/2013 3:12:22 PM | P | PASS |
|
|
permit finaled
|
FIR12-00423
| INSP-Final Inspection | 4/10/2013 | 4/10/2013 | 4/10/2013 3:11:10 PM | P | PASS |
|
|
permit finaled
|
FIR12-00423
| INSP-Sprinkler Rough-in/Hydro | 4/10/2013 | 4/10/2013 | 4/10/2013 3:10:08 PM | P | PASS |
|
|
jonathan Phone #: ###-####
|
FIR13-00161
| INSP-Final Inspection | 4/10/2013 | 4/10/2013 | 4/10/2013 10:00:29 AM | A | CANC |
|
|
Please call Jeff Packham before scheduling inspection to verify space will be accessible. Thanks. Phone #: ###-#### >> Inspection requested via web by Jeff Packham Inspection cancelled from web by: Jeff Packham
|
FIR12-00423
| INSP-Final Inspection | 4/9/2013 | 4/10/2013 | 4/10/2013 8:14:35 AM | A | FAIL |
|
|
doors are locked no access
|
FIR11-00152
| FIR-Aging Inspection | 4/10/2013 | 4/10/2013 | 4/10/2013 7:29:38 AM | | NR |
|
|
Jeff is going to follow up on job status per phone conversation.
|