Inspections for the day of: Tuesday, April 10, 2018.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorChad Schwendiman
TitleMEC-INSPECTOR
Phone #780-9549
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC18-01093 Final4/6/20184/10/20184/10/2018 4:09:28 PMPPASS
unit 102
MEC18-01536 Final4/5/20184/10/20184/10/2018 3:28:28 PMPPASS
PLEASE CONTACT KYLE FIRST TO ENSURE THE JOB IS COMPLETE BEFORE GOING. Phone #: ###-#### Inspection requested via web by Rick Borg
MEC18-01557 Final4/9/20184/10/20184/10/2018 2:53:14 PMPNR
Our Tech is installing this today so if you could do the inspection later afternoon that would be greatly appreciated. Our Techs number is ###-#### if you could call him when your headed his way. Phone #: ###-#### Inspection requested via web by Devony Bullard
MEC18-01575 Final4/9/20184/10/20184/10/2018 2:46:06 PMPPASS
installer Brandan ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt
MEC18-01530 Pressure Test4/10/20184/10/20184/10/2018 2:18:04 PMPFAIL
Phone #: ###-#### Inspection requested via web by Kaila Martarano - Gas pressure fail Gauge was down below 20lbs
MEC18-01530 Rough-in4/10/20184/10/20184/10/2018 2:17:33 PMPPASS
Phone #: ###-#### Inspection requested via web by Kaila Martarano - rough in on fireplace okay.
MEC17-04910 Pressure Test4/10/20184/10/20184/10/2018 1:49:28 PMPPART
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER - 60lb gas pass on piping from meter up to roff and across roof. 20lb gas on 2 drops from roof into building, 20lb gas pass on piping under floor up to above walk in cooler. 20lb gas pass on piping in the wall in the back right corner of the store
MEC18-00206 Rough-in4/9/20184/10/20184/10/2018 10:49:50 AMAPART
Requesting Rough-In inspection for Tuesday AM.

Contact: Jason Davidson Phone #: ###-#### Inspection requested via web by Melissa Kaae - Fire damper installation and clearances okay on fire/smoke dampers in electrical rooms next to elevators, and fire/smoke damper in upper area of lobby. need framing and sheetrock around all 4 sides of fire/smoke damper in the lower area of the lobby. duct seaal okay on duct in corridoor on 3rd and 2nd floor. okay to cover bathroom ceiling in room 112. need to remove fire caulk from around fire dampers, and fire/smoke dampers
MEC17-03454 Mec-Aging Inspection4/10/20184/10/20184/10/2018 6:40:08 AM CANC
MEC16-05529 Mec-Aging Inspection4/10/20184/10/20184/10/2018 6:39:03 AM DONE
Expired
MEC16-05529 DOC - Permit Expired4/10/20184/10/20184/10/2018 6:38:47 AMAPASS
MEC17-02128 Mec-Aging Inspection4/10/20184/10/20184/10/2018 6:38:09 AM CANC