BLD97-01576
| FIRE-Final Inspection | 4/10/2002 | 4/11/2002 | 4/11/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by Inspector: 409 On 4/10/2002 9:35:51 AM
|
BLD02-00063
| FIRE-Final Inspection | 4/10/2002 | 4/11/2002 | 4/11/2002 12:00:00 AM | A | PASS |
|
|
###-#### dryer vent penetrates floor ceiling assembly; not per the plans - mech has final pass; AHU for this space has detector for shutdown and worked properly 4/11/2002 10:26:58 AM
|
BLD96-02600
| FIRE-Conference | 4/11/2002 | 4/11/2002 | 4/11/2002 12:00:00 AM | A | PART |
|
|
Added by Inspector: 409 On 4/11/2002 10:30:31 AM met with John Wheeler and the 4 inch foam proportioner was installed per changes of the clacl'd area. Foam system still requires the annual test; will not final this permit until the foam test has been completed and the system proves to work properly
|
FIR01-00495
| INSP-Final Inspection | 4/11/2002 | 4/11/2002 | 4/11/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by Inspector: 409 On 4/11/2002 11:14:26 AM
|
BLD01-01647
| FIRE-Final Inspection | 4/11/2002 | 4/11/2002 | 4/11/2002 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 409 On 4/11/2002 3:17:13 PM
|
FIR02-00072
| INSP-Final Inspection | 4/11/2002 | 4/11/2002 | 4/11/2002 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 04/11/2002 at 08:20:23. Contact: ###-####. need knox box, sign on back door 4/11/2002 2:12:48 PM
|
BLD02-00270
| FIRE-Final Inspection | 4/11/2002 | 4/11/2002 | 4/11/2002 12:00:00 AM | P | PASS |
|
|
###-#### talked to tenant and GC and told them to get the address problem corrected with PDS to correct the permit problem 4/11/2002 3:18:15 PM
|
BLD01-00675
| FIRE-Final Inspection | 4/11/2002 | 4/11/2002 | 4/11/2002 12:00:00 AM | P | PASS |
|
|
###-####
|