PLM05-01069
| Plumbing Rough-in | 4/8/2005 | 4/11/2005 | 4/11/2005 12:00:00 AM | A | PART |
|
|
mike-- ###-#### --call 1st for access this was for the inspection under floor i did friday. 4/11/2005 9:03:38 AM
|
PLM05-01065
| Water and/or Sewer | 4/8/2005 | 4/11/2005 | 4/11/2005 12:00:00 AM | A | PASS |
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Barbara Moore sewer and strom drain connections ok storm drain connection moved to the existing stub to the north west corner of the building. 4/11/2005 9:25:03 AM
|
PLM05-01076
| Water and/or Sewer | 4/11/2005 | 4/11/2005 | 4/11/2005 12:00:00 AM | P | PASS |
|
|
joel ###-#### sw final ok 4/11/2005 3:23:56 PM
|
PLM05-00526
| Plumbing Rough-in | 4/11/2005 | 4/11/2005 | 4/11/2005 12:00:00 AM | P | CANC |
|
|
Scheduled by a contractor via Hello! on 4/11/2005 at 8:56:09 AM. Contact: ###-####. wrong permit phoned in. 4/11/2005 9:07:32 AM
|
PLM05-01081
| Sprinkler (Final) | 4/11/2005 | 4/11/2005 | 4/11/2005 12:00:00 AM | P | PASS |
|
|
mark ###-#### sp final ok 4/11/2005 3:08:32 PM
|
PLM05-01083
| Sprinkler (Final) | 4/11/2005 | 4/11/2005 | 4/11/2005 12:00:00 AM | P | PASS |
|
|
mark ###-#### sp final ok 4/11/2005 3:06:39 PM
|
PLM05-01084
| Sprinkler (Final) | 4/11/2005 | 4/11/2005 | 4/11/2005 12:00:00 AM | P | PASS |
|
|
mark ###-#### sp final ok 4/11/2005 3:06:25 PM
|
PLM05-01085
| Sprinkler (Final) | 4/11/2005 | 4/11/2005 | 4/11/2005 12:00:00 AM | P | PASS |
|
|
mark ###-#### sp final ok 4/11/2005 3:11:01 PM
|
PLM05-00648
| Final | 4/11/2005 | 4/11/2005 | 4/11/2005 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 4/11/2005 at 10:25:40 AM. Contact: ###-####. final ok 4/11/2005 3:02:51 PM
|
PLM05-00495
| Final | 4/11/2005 | 4/11/2005 | 4/11/2005 12:00:00 AM | P | PASS |
|
|
jeannette; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles final ok 4/11/2005 1:45:17 PM
|
PLM05-01008
| Water and/or Sewer | 4/11/2005 | 4/11/2005 | 4/11/2005 12:00:00 AM | P | PASS |
|
|
sw final ok 4/11/2005 1:03:19 PM
|