Inspections for the day of: Tuesday, April 11, 2017.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00040 INSP-Sprinkler Rough-in4/11/20174/11/20174/11/2017 2:44:44 PMPPASS
Rough to cover inspection for remaining underground complete, approved for cover.
FIR16-00040 INSP-Final Inspection4/11/20174/11/20174/11/2017 2:43:54 PMPCANC
Inspection request was for a rough to cover on remaining underground for northside supply, not a final inspection. This inspection request is cancelled and a rough in inspection will be generated.
FIR16-00556 INSP-Sprinkler Rough-in4/11/20174/11/20174/11/2017 2:41:09 PMPPART
Rough to cover inspection for levels 1 and 2 of pod 3 complete, approved for cover. Rough in inspection complete for level 3, tenting needs to be installed/inspected and passed before cover can be approved.
NAF17-00005 INSP-Final4/10/20174/11/20174/11/2017 11:04:20 AMPPASS
No fire sprinklers, no fire alarms, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
FIR17-00034 INSP-Final Inspection4/11/20174/11/20174/11/2017 10:02:35 AMAPASS
Final fire alarm inspection passed/complete
FIR16-00570 INSP-Sprinkler Rough-in4/10/20174/11/20174/11/2017 9:41:57 AMAPASS
Rough to cover inspection for area of work complete, approved for cover.
BLD16-03041 FIRE-Final Inspection4/6/20174/11/20174/11/2017 8:30:32 AMAPASS
No fire sprinklers, no monitored fire alarms, fire extinguishers are in place with current inspection tags. Exit lights in the south corridor will be changed to double sided exit lights as shown on city approved drawings (exit lights in place but only one sided at time of inspection, double side will be completed before final building inspection). Final life fire safey inspection passed/complete.