ELE13-03214
| ELE-Aging Inspection | 4/11/2018 | 4/11/2018 | 4/12/2018 12:33:26 PM | | FAIL |
|
|
still waiting on contractor to verify work and schedule inspections
|
ELE13-03227
| ELE-Aging Inspection | 4/11/2018 | 4/11/2018 | 4/12/2018 12:31:59 PM | | FAIL |
|
|
permit holder unable to contact and is making no attempt to schedule inspections
|
ELE17-01458
| Final | 4/11/2018 | 4/11/2018 | 4/11/2018 3:25:50 PM | P | PASS |
|
|
Inspection requested via web by Jeremy Cloud..building complete...ok to final...propane tank associated with building has pneumatic emergency shutoff...all associated piping inspected by others and no electrical work done under electrical permit
|
ELE18-01388
| Temporary Service | 4/10/2018 | 4/11/2018 | 4/11/2018 2:20:30 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Robert Murray....t/s u/g new ok
|
ELE18-00358
| Final | 4/10/2018 | 4/11/2018 | 4/11/2018 2:02:55 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Robert Murray....ok to final
|
ELE18-01342
| Final | 4/11/2018 | 4/11/2018 | 4/11/2018 1:14:22 PM | P | PASS |
|
|
Residential service change out Inspection after 2pm Please contact Lance Barg - 208 703 2035 Phone #: ###-#### Inspection requested via web by David Feller...job complete...ok to final
|
ELE18-01342
| Permanent Service | 4/11/2018 | 4/11/2018 | 4/11/2018 1:13:51 PM | P | PASS |
|
|
Residential service change out Inspection after 2pm Please contact Lance Barg - 208 703 2035 Phone #: ###-#### Inspection requested via web by David Feller...p/s u/g reconnect ok
|
ELE18-01198
| Electrical Rough-In | 4/11/2018 | 4/11/2018 | 4/11/2018 12:49:21 PM | P | PASS |
|
|
Phillip Phone #: ###-####...UL listed equipment verified...20A breaker in panel...ok
|
ELE18-01383
| Final | 4/10/2018 | 4/11/2018 | 4/11/2018 12:00:40 PM | A | NR |
|
|
This job was roughed in by another electrical contractor on a different permit. Please call Jared to meet you there ###-####. If you have any questions please feel free to contact Justin ###-####. Thanks!! Phone #: ###-#### Inspection requested via web by Clayton Morgan...not ready for final at this time
|
ELE16-02889
| Final | 4/11/2018 | 4/11/2018 | 4/11/2018 11:59:52 AM | P | PASS |
|
|
final to close out permit...contractor is aware of and ok with...work has been taken over by another electrical company. Reference permit ELE18-01383
|
ELE17-04043
| Final | 4/10/2018 | 4/11/2018 | 4/11/2018 10:51:40 AM | A | FAIL |
|
|
Garage code 7711E Phone #: ###-#### Inspection requested via web by Alan Lusk...job not complete...garage outlet not installed...did not go inside house
|
ELE18-01386
| Electrical Rough-In | 4/10/2018 | 4/11/2018 | 4/11/2018 10:34:54 AM | A | PASS |
|
|
underground and bonding Phone #: ###-#### Inspection requested via web by Ryan Wake...underground ok to cover...bonding 4 corners, cover, and 2 LED lights
|
ELE18-01157
| Final | 4/10/2018 | 4/11/2018 | 4/11/2018 10:08:46 AM | A | FAIL |
|
|
Logan Phone #: ###-####....no access to roof or service..Boise City requires rough in inspection to verify UL listed equipment, contractor shall be required to meet to get on roof and verify equipment
|
ELE18-01368
| Temporary Service | 4/10/2018 | 4/11/2018 | 4/11/2018 9:50:11 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Rowdy Monroe...t/s u/g new ok
|
ELE18-01369
| Temporary Service | 4/10/2018 | 4/11/2018 | 4/11/2018 9:49:47 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Rowdy Monroe...t/s u/g new ok
|
ELE18-01370
| Temporary Service | 4/10/2018 | 4/11/2018 | 4/11/2018 9:49:22 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Rowdy Monroe...t/s u/g new ok
|
ELE18-01387
| Electrical Rough-In | 4/10/2018 | 4/11/2018 | 4/11/2018 9:32:35 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by michael hunt...new walls for N offices and new walls for storage room...ok to cover
|
ELE18-01379
| Final | 4/10/2018 | 4/11/2018 | 4/11/2018 9:22:55 AM | A | PASS |
|
|
no home will be home- outside outback -Robert Phone #: ###-#### (1265 N Callahan is correct address TCH)...OCPD correct...ok to final
|
ELE18-01379
| Electrical Rough-In | 4/11/2018 | 4/11/2018 | 4/11/2018 9:22:29 AM | A | PASS |
|
|
no home will be home- outside outback -Robert Phone #: ###-#### (1265 N Callahan is correct address TCH)....new circuit out of exterior panel to disconnect
|
ELE18-01158
| Final | 4/10/2018 | 4/11/2018 | 4/11/2018 9:03:17 AM | A | FAIL |
|
|
karrigan Phone #: ###-####...no access to roof, Boise City requires rough inspection for UL verification, contractor must be onsite for future inspections
|
ELE18-01093
| Rough-In Permanent Service | 4/10/2018 | 4/11/2018 | 4/11/2018 8:47:15 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Darryn Coburn...rough ok to cover...p/s u/g new ok
|
ELE18-01367
| Electrical Rough-In | 4/10/2018 | 4/11/2018 | 4/11/2018 8:23:07 AM | A | PASS |
|
|
Meter and Pedestal Service Inspection...questions please call Tom ###-#### Phone #: ###-#### Inspection requested via web by Bonnie Page...ok to pour...grounding and pipes
|