FIR18-00093
| INSP-Sprinkler Rough-in | 4/11/2018 | 4/11/2018 | 4/11/2018 3:40:10 PM | P | PASS |
|
|
Rough-in passed and piping can be covered. I noted two areas that need modifications though. The first is in the southeast kitchen a pendant head needs to be added and in the freezer area one pendant needs relocated.
RIck Phone #: ###-####
|
FIR17-00771
| INSP-Sprinkler Rough-in | 4/11/2018 | 4/11/2018 | 4/11/2018 3:17:49 PM | P | PASS |
|
|
Overhead rough-in passed. The piping above the hard lids can be covered. Another inspection will be required for the arm overs when the T-bar ceiling is installed.
Jonathan Phone #: ###-####
|
FIR17-00771
| INSP-Sprinkler Rough-in/Hydro | 4/11/2018 | 4/11/2018 | 4/11/2018 3:16:27 PM | P | PASS |
|
|
Supply line, underground hydro test passed
|
FIR18-00277
| INSP-Sprinkler Rough-in/Hydro | 4/11/2018 | 4/11/2018 | 4/11/2018 3:13:13 PM | P | PART |
|
|
Overhead rough-in passed. I noted that the plans call for quick responce heads in the scope of work but not all heads are quick responce. I noted that a short corridor outside of the sprinkler scope of work appears to be in the building scope of work but has a standard responce head that is open to an area with quick responce heads. I noted a Storage room adjacent to the scope of work where the small room rule is being utilized which is not allowed. I noted another room in the building scope of work where two sidwall heads are located one above another and again are only standard responce. Piping is ok for cover since the above noted items can be verified at final. Tenting inspection is still needed.
Brian Phone #: ###-####
|
BLD17-02426
| FIRE-Final Inspection | 4/10/2018 | 4/11/2018 | 4/11/2018 2:05:29 PM | A | CANC |
|
|
No approvedd plans or small documents on site. The project related fire alarm and fire sprinkler permits need addressed.
Phone #: ###-#### Inspection requested via web by David Scaggs
|
FIR17-00460
| INSP-Final Inspection | 4/10/2018 | 4/11/2018 | 4/11/2018 2:04:33 PM | A | CANC |
|
|
The project related fire alarm permit has not been scheduled.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
FIR17-00461
| INSP-Final Inspection | 4/10/2018 | 4/11/2018 | 4/11/2018 2:02:53 PM | A | FAIL |
|
|
The sprinkler heads in the second floor mechanical rooms still had the shipping caps on and appeared they may need height adjustment to fit the canopies. The fire riser devices have been tested.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
FIR17-00493
| INSP-Final Inspection | 4/10/2018 | 4/11/2018 | 4/11/2018 2:00:00 PM | A | PASS |
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by Sam Ball
|
BLD17-02425
| FIRE-Final Inspection | 4/10/2018 | 4/11/2018 | 4/11/2018 1:58:56 PM | A | FAIL |
|
|
No plans or small documents on site. Project related fire sprinkler permit failed.
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD17-03618
| FIRE-Final Inspection | 4/9/2018 | 4/11/2018 | 4/11/2018 11:31:24 AM | A | FAIL |
|
|
Todays inspection was just to meet/provide a correction notice for the existing deficient fire alarm system. It appears that the owner is going to move in the direction of an upgrade agreement. I discussed with Curtis the need to final all of the fire sprinkler permits, and go through the life safety items such as the emergency lights, exit signs....ect.
Curtis Phone #: ###-####
|
FIR17-00670
| INSP-Final Inspection | 4/10/2018 | 4/11/2018 | 4/11/2018 10:06:42 AM | P | CANC |
|
|
George Jess is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR17-00692
| INSP-Final Inspection | 4/10/2018 | 4/11/2018 | 4/11/2018 10:05:26 AM | A | CANC |
|
|
Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
BLD17-01166
| FIRE-Final Inspection | 4/10/2018 | 4/11/2018 | 4/11/2018 9:53:26 AM | A | PASS |
|
|
Life safety passed. Hydraulic closures are required on the smoke doors for the building inspection.
cecle Phone #: ###-####
|
FIR17-00366
| INSP-Final Inspection | 4/10/2018 | 4/11/2018 | 4/11/2018 9:52:21 AM | A | PASS |
|
|
Permit finaled
Call prior to going Phone #: 2089411846 >> Inspection requested via mobile web by SVC Brian A
|
BLD18-00308
| FIRE-Final Inspection | 4/5/2018 | 4/11/2018 | 4/11/2018 9:51:53 AM | A | FAIL |
|
|
Provide annual inspection tag for the fire extinguisher, repair or remove the non-functional exit sign and emergency light.
15 mins heads up please- Brad Phone #: ###-####
|