FIR05-00238
| FIR-Aging Inspection | 4/13/2006 | 4/13/2006 | 4/17/2006 3:25:21 PM | | DONE |
|
|
wip
|
BLD05-03305
| FIRE-Final Inspection | 4/12/2006 | 4/13/2006 | 4/13/2006 5:45:20 PM | A | PASS |
|
|
Life safety passed final inspection.
|
FIR06-00081
| INSP-Final Inspection | 4/13/2006 | 4/13/2006 | 4/13/2006 5:43:17 PM | P | PASS |
|
|
Fire alarm finaled.
|
FIR05-00449
| INSP-Alarm Testing | 4/10/2006 | 4/13/2006 | 4/13/2006 4:15:27 PM | A | PART |
|
|
Tested ground level smoke detectors at lobby area, need to provide one additional SD above front entrance as coverage is obstructed by beam blockage, fire alarm wire shall be attatched to the building structure, tested notification and detection devices at the mechanical penthouse, the west stair fan was not functional for testing, tested all air handling units in the fan rooms on floors 3 through 11, need to provide dates on NAC batteries at 6th and 8th floors, sprinkler monitoring to be tested at next inspection.
|
BLD05-01346
| FIRE-Final Inspection | 4/13/2006 | 4/13/2006 | 4/13/2006 1:49:30 PM | P | PASS |
|
|
The project related alarm permit has been finaled, fire life safety for the permitted work scope is satisfactory.
|
FIR05-00875
| INSP-Final Inspection | 4/12/2006 | 4/13/2006 | 4/13/2006 1:35:40 PM | P | PASS |
|
|
c/n items are completed, final testing passed inspection, permit finaled.
|
FIR05-00555
| INSP-Final Inspection | 4/11/2006 | 4/13/2006 | 4/13/2006 11:10:49 AM | A | PASS |
|
|
The required corrections have been verified for completion, fire alarm permit finaled.
|
FIR06-00053
| INSP-Supply line flush | 4/12/2006 | 4/13/2006 | 4/13/2006 10:40:33 AM | A | PART |
|
|
UG supply line flush performed satisfactory, the PIV has been adjusted to the required height above finish grade.
|
FIR05-00709
| INSP-Sprinkler Rough-in/Hydro | 4/13/2006 | 4/13/2006 | 4/13/2006 9:53:49 AM | A | PART |
|
|
Overhead rough-in corrections have been made, 3rd floor is acceptable for cover.
|