BLD02-00266
| BLD-Conference | 4/11/2003 | 4/14/2003 | 4/14/2003 12:00:00 AM | A | PASS |
|
|
dave @ devcon...shaft & framing; ###-####; add 18" clr at pull side door at lower level, verify 18" clr to combustibles for hood add drywall as needed...ok to continue, obtain all trade & fire insps prior to frame insp. 4/14/2003 11:40:17 AM
|
BLD02-00369
| BLD-Framing/Rough-in | 4/11/2003 | 4/14/2003 | 4/14/2003 12:00:00 AM | A | PART |
|
|
prelim. only...reviewed eng's observation letter: need sister 2x4's to 3x4 studs at grid 9.4 & WB (BW5 to be 4x4)...addn of 16ga. straps at sills/plates cut for plbg req'd...replace a-bolts displaced by block-outs...need clarify 5" holes for bolts...6" spec'd (when cast, these are epoxied...) WIP 4/14/2003 3:59:21 PM
|
BLD02-03024
| BLD-Final | 4/14/2003 | 4/14/2003 | 4/14/2003 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 4/14/2003 at 7:21:06 AM. Contact: ###-####...l/c issued 4/14/2003 9:13:57 AM
|
BLD02-00370
| BLD-Conference | 4/14/2003 | 4/14/2003 | 4/14/2003 12:00:00 AM | A | PART |
|
|
4hr wall... clarify framing detail ...keep c/n. 4/14/2003 11:42:24 AM
|
BLD03-00553
| BLD-Framing/Rough-in | 4/14/2003 | 4/14/2003 | 4/14/2003 12:00:00 AM | P | FAIL |
|
|
House unlocked-please go through back door; Phone #: ###-#### Internet Inspection Request from: Gary Gettman, c/n, air seal, brg wall? verify hvac r/i..ok to insul only, meet energy code. 4/14/2003 4:33:52 PM
|
BLD02-00369
| BLD-Framing/Rough-in | 4/14/2003 | 4/14/2003 | 4/14/2003 12:00:00 AM | P | PART |
|
|
reviewed spec insp reports, need eng's ok forpossible sub-spec Field Cure samples/tests for concrete...awaiting 28 & 56 day results. 4/15/2003 11:07:34 AM May show w/ BLD02-00199 4/15/2003 11:07:56 AM
|
BLD02-00371
| BLD-Conference | 4/14/2003 | 4/14/2003 | 4/14/2003 12:00:00 AM | P | PASS |
|
|
4hr walls...build wall per eng'g 4/14/2003 4:02:38 PM
|
BLD02-00372
| BLD-Conference | 4/14/2003 | 4/14/2003 | 4/14/2003 12:00:00 AM | P | PASS |
|
|
4hr walls...build wall per eng'g. 4/14/2003 4:02:59 PM
|
BLD02-00373
| BLD-Conference | 4/14/2003 | 4/14/2003 | 4/14/2003 12:00:00 AM | P | PASS |
|
|
re 4hr walls...build per eng'g 4/14/2003 5:45:50 PM
|
BLD02-00375
| BLD-Conference | 4/14/2003 | 4/14/2003 | 4/14/2003 12:00:00 AM | P | PASS |
|
|
4hr walls , need clarify stud/brace details ... 4/14/2003 4:01:03 PM 4/14/2003 4:01:21 PM
|
BLD02-00374
| BLD-Conference | 4/14/2003 | 4/14/2003 | 4/14/2003 12:00:00 AM | P | PASS |
|
|
4hr walls, remove gyp, rebuild wall per engs detail 4/14/2003 4:02:09 PM
|