Inspections for the day of: Friday, April 14, 2006.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR05-00128 FIR-Aging Inspection4/14/20064/14/20064/20/2006 12:40:11 PM DONE
Spoke to the alarm contractor who said the project is not yet completed and still in progress due to a phased remodel.
FIR05-00297 INSP-Final Inspection4/13/20064/14/20064/17/2006 9:52:57 AMPNR
Project is not ready for final inspection.
BLD05-03484 FIRE-Final Inspection4/13/20064/14/20064/17/2006 9:49:17 AMAFAIL
Door hardware at the west wooden door is not installed at this time, need to test mag lock drop out at three locations upon fire alarm activation, free standing signs at the emergency exit only must not obstruct the path of egress, no occupant sensors are installed-the doors are equipped with panic hardware.
BLD04-02927 FIRE-Final Inspection4/13/20064/14/20064/17/2006 9:45:18 AMAFAIL
Remove deadbolts at two locations on exit doors that are not the main entry/exit, provide address numbers facing Bown Way, repair emergency discharge light at the main entry, the project related fire sprinkler permit for the medical gas closet must be requested for inspection and approved prior to building life safety final (it appears there are some defficiencies related to the fire sprinkler at this time).
FIR05-00075 INSP-Final Inspection4/13/20064/14/20064/14/2006 3:50:33 PMANR
Project not ready for inspection due to related fire sprinkler issues and a non-functional elevator.
FIR05-00425 INSP-Sprinkler Rough-in/Hydro4/13/20064/14/20064/14/2006 3:47:10 PMAPART
6th floor cover inspection related to the fire sprinklers at the hard lid areas is acceptable.
FIR06-00228 INSP-Final Inspection4/13/20064/14/20064/14/2006 3:43:59 PMAPASS
Fire sprinkler work has been completed satisfactory, permit finaled.
FIR06-00205 INSP-Sprinkler Rough-in4/13/20064/14/20064/14/2006 3:43:03 PMAPART
Overhead rough-in is good for cover at the drop ceiling areas, need to verify the existing system and fire pump are current with an annual inspection, final pending installation of ceiling tile and escutcheons.
FIR05-00449 INSP-Alarm Testing4/10/20064/14/20064/14/2006 1:00:47 PMAPART
All fire sprinkler monitoring points including tampers, flows, tank and pump supervision tested today, main riser flow and tamper point corrected while on site, re-tested west stair fan for functionality on alarm, voice evac failed to function on alarm at the 6th, 10th and 11th floors today-have incurred problems with intermittent failure of the voice system on three separate inspections during this project.
FIR05-00052 INSP-Final Inspection4/13/20064/14/20064/14/2006 9:36:22 AMACANC
This inspection is to demonstrate elevator recall in upgraded elevators, please do inspection as close to 8:00 A.M. as possible Internet Inspection Request from: Terry Owsley Inspection cancelled from web by: Terry Owsley
BLD04-02927 FIRE-Final Inspection4/14/20064/14/20064/14/2006 12:00:00 AMPDONE
###-#### - scott
FIR05-00297 INSP-Final Inspection4/13/20064/14/20064/13/2006 2:38:20 PMACANC
Contact: Jason; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley