Inspections for the day of: Wednesday, April 14, 2010.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorClint A Smith
TitleEROSION CONTROL INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC09-00812 Random Inspection4/14/20104/14/20104/14/2010 4:11:02 PMPPART
liner has been put in place at the storm water out in the east end of Quinns Pond where erosion has occured. Liner within the channel still needs maintenance to occur where it has degrated.
ESC07-00198 Aging Inspection4/14/20104/14/20104/14/2010 2:37:44 PM DONE
ESC07-00198 DOC - Permit Finaled4/14/20104/14/20104/14/2010 2:37:36 PMPPASS
ESC07-00197 Aging Inspection4/14/20104/14/20104/14/2010 2:37:30 PM DONE
ESC07-00197 DOC - Permit Finaled4/14/20104/14/20104/14/2010 2:37:25 PMPPASS
ESC07-00196 Aging Inspection4/14/20104/14/20104/14/2010 2:37:17 PM DONE
ESC07-00196 DOC - Permit Finaled4/14/20104/14/20104/14/2010 2:37:12 PMPPASS
ESC10-00280 Site Preparation4/14/20104/14/20104/14/2010 2:18:51 PM NR
ESC10-00277 Site Preparation4/14/20104/14/20104/14/2010 1:55:17 PM PASS
ESC10-00260 Site Preparation4/14/20104/14/20104/14/2010 1:27:59 PM PASS
ESC10-00267 Complaint Inspection4/14/20104/14/20104/14/2010 1:27:51 PMPPART
Explained the proper method of concrete tool clean up and where the appoved area is located either within the provided washoutpit or an external containment that is located at the back of walk.
ESC09-00352 General Inspection4/13/20104/14/20104/14/2010 10:02:01 AMAPART
Pedestrian Bridge:
Due to the concern that occured with the dewatering basin last night, the RP is responsible for altering there practices of dewatering to stay compliant. Told the RP that only non turbid water should be discharge into a well vegitative area and or back into Wallings Creek. Also capture all turbid water if it exceeds the DEQ allowable limits to allow sediment to drop within the provided dewatering basin. Once water is within the allowable limit of back ground, than a dischage would be accepted. Will re-inspect on 4/15/10 PM.
ESC10-00226 Site Preparation4/14/20104/14/20104/14/2010 9:07:02 AM PASS