Inspections for the day of: Tuesday, April 14, 2015.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorKatie Marron
TitleFIRE INSPECTOR
Phone #395-7809
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00531 INSP-Sprinkler Rough-in4/10/20154/14/20154/14/2015 4:42:46 PMPFAIL
Fail. Missing hangers at numerous locations and a branch line not connected to the main. Will verify corrections at next inspection scheduled for 4/15/15.
FIR14-00815 INSP-Sprinkler Rough-in/Hydro4/7/20154/14/20154/14/2015 3:48:51 PMPPART
Hydro test on dry system #1 satisfactory completed.
FIR13-00142 INSP-Sprinkler Rough-in/Hydro4/7/20154/14/20154/14/2015 3:14:51 PMPDEFR
Wrong inspection type, request intended for final.
FIR14-00735 INSP-Sprinkler Rough-in/Hydro4/14/20154/14/20154/14/2015 11:26:53 AMPPART
Area D Porte Cochere
dry system ok to cover per plans. Entry vestibule was not complete at this time.
FIR15-00071 INSP-Final Inspection4/14/20154/14/20154/14/2015 10:42:18 AMPPART
Final walk through completed at 2nd floor.
FIR15-00071 INSP-Sprinkler Rough-in4/14/20154/14/20154/14/2015 10:40:56 AMPPART
1st Floor ok to cover at drop ceiling per plan.
BLD15-00120 FIRE-Final Inspection4/13/20154/14/20154/14/2015 9:22:18 AMAPASS
All previously noted items corrected. FIre Life Safety passed. Noted one ceiling tile to be replaced and plans need to be resubmitted to identify new corridor door.
FIR15-00166 INSP-Final Inspection4/14/20154/14/20154/14/2015 9:20:06 AMAPASS
Sprinkler permit finaled
FIR14-00735 INSP-Sprinkler Rough-in4/13/20154/14/20154/14/2015 8:09:54 AMACANC
Rough in Porte Cochere - Dry
Please contact Leroy 30 min prior ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt