BLD16-00907
| BLD-Framing/Rough-in | 4/14/2016 | 4/14/2016 | 4/14/2016 3:46:13 PM | P | PASS |
|
|
would like call ahead; Kent Phone #: ###-####. Ok to insulate.
|
BLD15-03823
| BLD-Final | 4/14/2016 | 4/14/2016 | 4/14/2016 3:07:56 PM | P | PART |
|
|
Call 30 minutes before // Hamish Phone #: ###-####. Ok for temp occ. Need RFI from enfineer on alternate parapet bracing and transitions into roll in showers.
|
BLD15-01921
| BLD-Framing/Rough-in | 4/14/2016 | 4/14/2016 | 4/14/2016 2:44:23 PM | P | PASS |
|
|
Kent-early if possible Phone #: ###-####. All framing issues have been resolved. Ok to insulate. Advise Kent to reschedule mech. rough in inspection and noted to him the correction notice from mech. to resubmit plans.
|
BLD16-00804
| BLD-Framing/Rough-in | 4/14/2016 | 4/14/2016 | 4/14/2016 2:42:45 PM | P | PASS |
|
|
would like call ahead; Dennis Phone #: ###-####
|
MIS16-00118
| BLD-Final | 4/14/2016 | 4/14/2016 | 4/14/2016 2:30:33 PM | P | DONE |
|
|
as per Tim Woodard- request to verify c of o of Boise Granit on east end of building. A correction notice was issued to provide T.I. plans and get all required inspedtions to obtain a certificate of occupancy.
|
BLD16-00722
| BLD-Final | 4/14/2016 | 4/14/2016 | 4/14/2016 2:28:46 PM | P | PASS |
|
|
JERIMY Phone #: ###-####
|
BLD16-00299
| BLD-Wall Bracing | 4/14/2016 | 4/14/2016 | 4/14/2016 2:28:43 PM | P | PASS |
|
|
Bendi Phone #: ###-####
|
BLD16-00722
| DOC - Permit Finaled | 4/14/2016 | 4/14/2016 | 4/14/2016 2:28:19 PM | P | PASS |
|
|
|
GCB15-00090
| GCB-Fndatn/slab ins/fld vent | 4/13/2016 | 4/14/2016 | 4/14/2016 11:11:27 AM | A | PASS |
|
|
Chris ###-#### - rebar insp. east exterior stemwall ok.
|
BLD16-00783
| BLD-Framing/Rough-in | 4/13/2016 | 4/14/2016 | 4/14/2016 10:20:29 AM | A | PASS |
|
|
Preston Phone #: ###-####
|
BLD15-04503
| BLD-Framing/Rough-in | 4/13/2016 | 4/14/2016 | 4/14/2016 9:59:51 AM | A | PART |
|
|
Cecle Phone #: ###-####. Interior steel stud framed walls and hardlid ok. Noted opening protection issues behind transfer shower at rated wall. NO rock installed behind shower, also membrane protection for shower valve?
|
BLD16-00896
| BLD-Framing/Rough-in | 4/13/2016 | 4/14/2016 | 4/14/2016 9:13:17 AM | A | PASS |
|
|
SPENCE Phone #: ###-####. Interior wood stud walls ok.
|
BLD15-01551
| BLD-Final | 4/13/2016 | 4/14/2016 | 4/14/2016 8:58:19 AM | A | PASS |
|
|
Jake Phone #: ###-####. Ok for perm occ.
|