PLM02-00938
| Sprinkler (Final) | 4/11/2002 | 4/15/2002 | 4/15/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by Inspector: 330 On 4/11/2002 10:19:46 AM just look for a test tag, someone stole the one that was on there.
|
PLM02-00966
| Sprinkler (Final) | 4/12/2002 | 4/15/2002 | 4/15/2002 12:00:00 AM | A | PASS |
|
|
###-####
|
PLM02-00221
| Final | 4/12/2002 | 4/15/2002 | 4/15/2002 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 04/12/2002 at 16:21:09. Contact: ###-####. sprinkler permit required prior to fina l inspection, no access to building for final 4/15/2002 9:10:17 AM
|
PLM02-00977
| Sprinkler (Final) | 4/12/2002 | 4/15/2002 | 4/15/2002 12:00:00 AM | A | PASS |
|
|
STEVE ###-####
|
PLM02-00986
| Sprinkler (Final) | 4/15/2002 | 4/15/2002 | 4/15/2002 12:00:00 AM | A | PASS |
|
|
###-#### christine final ok 4/15/2002 4:05:53 PM
|
PLM02-00987
| Water and/or Sewer | 4/15/2002 | 4/15/2002 | 4/15/2002 12:00:00 AM | P | PASS |
|
|
###-#### steve swr & water
|
PLM02-00988
| Sprinkler (Final) | 4/15/2002 | 4/15/2002 | 4/15/2002 12:00:00 AM | P | PASS |
|
|
###-#### christine
|
PLM02-00394
| Final | 4/15/2002 | 4/15/2002 | 4/15/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by Inspector: 330 On 4/15/2002 1:29:02 PM
|
PLM01-03729
| Water and/or Sewer | 4/15/2002 | 4/15/2002 | 4/15/2002 12:00:00 AM | P | NR |
|
|
Added by Inspector: 330 On 4/15/2002 3:44:05 PM I was out twice today but they were in the midst of a cluster
|
PLM02-00221
| Final | 4/15/2002 | 4/15/2002 | 4/15/2002 12:00:00 AM | P | CANC |
|
|
Added by Inspector: 330 On 4/15/2002 4:05:26 PM final ok
|
PLM02-00662
| Final | 4/15/2002 | 4/15/2002 | 4/15/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 04/15/2002 at 09:17:51. Contact: ###-####.
|
PLM02-00800
| Plumbing Rough-in | 4/15/2002 | 4/15/2002 | 4/15/2002 12:00:00 AM | P | PASS |
|
|
###-#### TOM
|