Inspections for the day of: Thursday, April 15, 2010.
Number of inspections: 2
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorSteven Webb
Title 
Phone #794-9491
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC09-00352 Conference4/15/20104/15/20104/15/2010 3:08:15 PMPPASS
Ped. Bridge: Reviewed de-watering and discussion took place on further scope of work. Met with Wetlands Group and Brighton plus Inspector 460. Discharge of water is required to be within state water quality standards for turbidity. Upon completion site stabilzation will be expected.
ESC10-00268 Site Preparation4/15/20104/15/20104/15/2010 7:50:33 AM CANC
Passed by inspector 316 on 4/13/10