BLD14-00140
| BLD-Final | 4/15/2014 | 4/15/2014 | 4/15/2014 5:02:40 PM | P | PART |
|
|
Met with Daryl, (electrical inspector) on site to review groundeing requirements for the infusion room. It was determined that this area needs to have the seperate grounding as per NEC requirements. Noted to contractor that once a new electrical permit has been issued for this work, a 30 day temp. occ. would be granted while this work is completed and other portions of building could be used.
|
BLD13-03557
| BLD-Final | 4/14/2014 | 4/15/2014 | 4/15/2014 4:25:52 PM | P | NR |
|
|
pat Phone #: ###-####
|
BLD14-00340
| BLD-Final | 4/15/2014 | 4/15/2014 | 4/15/2014 2:37:54 PM | P | PASS |
|
|
please call for entry if no one is home Phone #: ###-#### >> Inspection requested via web by kevin debelloy
|
BLD14-00340
| DOC - Permit Finaled | 4/15/2014 | 4/15/2014 | 4/15/2014 2:37:37 PM | P | PASS |
|
|
|
BLD13-03519
| BLD-Wall cover | 4/15/2014 | 4/15/2014 | 4/15/2014 1:39:23 PM | P | CANC |
|
|
|
BLD13-01688
| BLD-Final | 4/15/2014 | 4/15/2014 | 4/15/2014 1:39:09 PM | P | PART |
|
|
Charles Phone #: ###-####. Phase 1a patient addition only ok to occupy.
|
BLD13-03523
| BLD-Energy code compliance | 4/14/2014 | 4/15/2014 | 4/15/2014 1:38:04 PM | A | PASS |
|
|
Insulation at firewall Phone #: ###-#### >> Inspection requested via web by Brian Stark
|
BLD13-03523
| BLD-Wall cover | 4/15/2014 | 4/15/2014 | 4/15/2014 1:37:54 PM | P | PASS |
|
|
Insulation at firewall Phone #: ###-#### >> Inspection requested via web by Brian Stark. 1st. floor firewall ok.
|
BLD13-03522
| BLD-Energy code compliance | 4/14/2014 | 4/15/2014 | 4/15/2014 1:37:21 PM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark
|
BLD13-03522
| BLD-Wall cover | 4/15/2014 | 4/15/2014 | 4/15/2014 1:37:09 PM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark. 1st. floor firewall ok.
|
BLD13-03521
| BLD-Energy code compliance | 4/14/2014 | 4/15/2014 | 4/15/2014 1:36:37 PM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark
|
BLD13-03521
| BLD-Wall cover | 4/15/2014 | 4/15/2014 | 4/15/2014 1:36:17 PM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark. 1st. floor firewall ok.
|
BLD13-03519
| BLD-Energy code compliance | 4/14/2014 | 4/15/2014 | 4/15/2014 1:35:45 PM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark
|
BLD13-03519
| BLD-Wall cover | 4/15/2014 | 4/15/2014 | 4/15/2014 1:35:34 PM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark. 1st. floor firewall ok.
|
BLD13-03362
| BLD-Wall cover | 4/14/2014 | 4/15/2014 | 4/15/2014 12:18:06 PM | A | PASS |
|
|
Sheetrock shear fastening schedule Phone #: ###-#### >> Inspection requested via web by Brian Stark. Interior wall bracing ok.
|
BLD13-03364
| BLD-Wall cover | 4/14/2014 | 4/15/2014 | 4/15/2014 12:17:37 PM | A | PASS |
|
|
Sheetrock shear fastening schedule Phone #: ###-#### >> Inspection requested via web by Brian Stark. Interior wall bracing ok.
|
BLD14-00140
| BLD-Final | 4/14/2014 | 4/15/2014 | 4/15/2014 12:17:02 PM | A | CANC |
|
|
Tom Phone #: ###-####. Moved to pm. Meeting electrical inspector on site to verify correct grounding and wiring methods in infusion room.
|
BLD14-00645
| BLD-Final | 4/14/2014 | 4/15/2014 | 4/15/2014 12:12:32 PM | A | PASS |
|
|
Phone #: ###-####
|
BLD14-00645
| DOC - Permit Finaled | 4/15/2014 | 4/15/2014 | 4/15/2014 12:12:09 PM | P | PASS |
|
|
All work appeared to be done in accordance with local codes and ordinances.
|
BLD13-01688
| BLD-Footing | 4/14/2014 | 4/15/2014 | 4/15/2014 12:05:36 PM | A | PASS |
|
|
SHawn Phone #: ###-####. footings for new patio cocer.
|