Inspections for the day of: Wednesday, April 15, 2015.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorKatie Marron
TitleFIRE INSPECTOR
Phone #395-7809
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00708 INSP-Sprinkler Rough-in4/15/20154/15/20154/15/2015 4:49:15 PMPFAIL
Bldg G wet system 2nd Floor
, no approval for cover at this time due to significant field modifications, requiring plan resubmittial. Modifications include changes to remote area.
FIR14-00531 INSP-Sprinkler Rough-in4/14/20154/15/20154/15/2015 4:10:59 PMAPART
Floors 4, 3 and podium in tower 4 living quarters ok to cover, except room 204 with overspaced bedroom head and room 200 missing closet head. Soffits in tower 3 ok to cover.
FIR13-00167 INSP-Sprinkler Rough-in4/15/20154/15/20154/15/2015 4:07:56 PMPCANC
Cancelled to be rescheduled per phone conversation with contractor.
FIR14-00815 INSP-Sprinkler Rough-in4/13/20154/15/20154/15/2015 3:12:02 PMPDEFR
Rescheduled for 4/16 per discussion with contractor
BLD15-00071 FIRE-Final Inspection4/15/20154/15/20154/15/2015 3:09:25 PMPFAIL
Contractor to replace door hardware according to plan, exiting discharge light at service entrance, contractor not prepared to test duct smoke detectors and building number needs to be contrasting.
FIR15-00112 INSP-Sprinkler Rough-in/Hydro4/14/20154/15/20154/15/2015 3:07:00 PMAPART
Second Flr Hydrostatic testing of new system piping complete ok. Heads at new ceilings and tie in incomplete at this time.
BLD14-01578 FIRE-Final Inspection4/15/20154/15/20154/15/2015 11:16:59 AMPPASS
Remainder of scope of work completed, building numbers have been posted final life safety approved.
NAF15-00001 INSP-Supply line flush4/14/20154/15/20154/15/2015 9:42:43 AMAFAIL
Insufficient means provided to complete flushing.
BLD15-00395 FIRE-Final Inspection4/14/20154/15/20154/15/2015 12:00:00 AMACANC
Larry Phone #: ###-####
FIR13-00142 INSP-Final Inspection4/14/20154/15/20154/14/2015 3:18:27 PMAPASS
Final walk through completed. Verified functional flow switch. Contractor to replace missing echeons/patch hole at mechanical closets adjacent to riser room, and to post sign at riser room door per review notes.