FIR08-00234
| INSP-Final Inspection | 4/13/2009 | 4/16/2009 | 4/17/2009 7:08:38 PM | P | PART |
|
|
Tested notification devices for the 18th thru basement levels via one manual pull station per level, noted one non-functional speaker strobe on the 14th floor corridor, need to verify MP's at the 18th floor balcony are wp, noted audibility measurements at several condos and common corridors on the 5th thru 11th levels is not sufficient, replaced av's in the basement corridor tested okay, provide strobe notification at the fire command center as discussed. Inspection completed 4/16..
|
FIR08-00018
| INSP-Final Inspection | 4/14/2009 | 4/16/2009 | 4/16/2009 4:10:58 PM | A | NR |
|
|
Work in progress to relocate floor control tamper valves, dry system trip testing could not be completed due to floor coating underway at the parking levels.
|
BLD07-00007
| FIRE-Final Inspection | 4/15/2009 | 4/16/2009 | 4/16/2009 4:08:13 PM | A | PASS |
|
|
Project related fire permits finaled, fire life safety approved for final.
|
FIR09-00245
| INSP-Final Inspection | 4/16/2009 | 4/16/2009 | 4/16/2009 4:06:43 PM | P | PASS |
|
|
Scope of fire sprinkler permit work completed, inspection finaled.
|
BLD09-00002
| FIRE-Final Inspection | 4/15/2009 | 4/16/2009 | 4/16/2009 4:05:37 PM | A | PASS |
|
|
Noted correction items verified for completion, fire life safety passed.
|