ELE14-02362
| Final | 4/15/2015 | 4/16/2015 | 4/16/2015 2:57:40 PM | A | PASS |
|
|
We are requesting a final inspection for this project tomorrow 4/16/15. Our contact for this is Todd Hall @###-####. Thank you Phone #: ###-#### Inspection requested via web by Clint Tate ok final, signed card
|
ELE15-00977
| Electrical Rough-In | 4/15/2015 | 4/16/2015 | 4/16/2015 10:11:43 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Chris Chesnut corrections made, ok cover floor heat
|
ELE15-01046
| Electrical Rough-In | 4/15/2015 | 4/16/2015 | 4/16/2015 9:29:45 AM | A | PASS |
|
|
Trench and base inspection for (2ea) bollard lights and (1ea) monument light Phone #: ###-#### Inspection requested via web by steve ragan ok cover u/g
|
ELE15-01044
| Final | 4/15/2015 | 4/16/2015 | 4/16/2015 8:55:04 AM | A | PASS |
|
|
Installed and wired new dedicated 15 amp 120 volt circuit to a new twist lock receptacle from panel B circuit breaker 34, the receptacle is to the left of panel B Phone #: ###-#### Inspection requested via web by Dan Mitchell ok final
|
ELE15-01044
| Electrical Rough-In | 4/15/2015 | 4/16/2015 | 4/16/2015 8:36:31 AM | A | PASS |
|
|
Installed and wired new dedicated 15 amp 120 volt circuit to a new twist lock receptacle from panel B circuit breaker 34, the receptacle is to the left of panel B Phone #: ###-#### Inspection requested via web by Dan Mitchell called to add strap out of panel B, ri ok
|
ELE15-00174
| Electrical Rough-In | 4/15/2015 | 4/16/2015 | 4/16/2015 8:06:29 AM | A | PASS |
|
|
see 4-15 request
|