Inspections for the day of: Wednesday, April 17, 2002.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorLee Rice
TitlePLM-CHIEF INSPECTOR
Phone #794-9486
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM02-01014 Sprinkler (Final)4/16/20024/17/20024/17/2002 12:00:00 AMAPASS
###-#### CAROL
PLM02-00514 Final4/16/20024/17/20024/17/2002 12:00:00 AMAPASS
###-####
PLM02-00759 Plumbing Rough-in4/16/20024/17/20024/17/2002 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 04/16/2002 at 18:16:39. Contact: ###-####.test did not hold ,gave couple of pointers. 4/17/2002 2:42:14 PM
PLM02-00916 Water and/or Sewer4/17/20024/17/20024/17/2002 12:00:00 AMPPASS
jim ###-####
PLM01-01197 Final4/17/20024/17/20024/17/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 04/17/2002 at 08:58:24. Contact: ###-####.
PLM02-00039 Plumbing Rough-in4/17/20024/17/20024/17/2002 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 04/17/2002 at 10:01:51. Contact: ###-####. waste test failed, needs nail plates, bath tub r/i upstairs won't work. Gary, you may want to have him call you back when shower and tubs are set also. 4/17/2002 3:24:33 PM also, I asked if water line had been ran yet? note posted on window by front door. 4/17/2002 3:28:07 PM
PLM99-04020 Sprinkler (Final)4/17/20024/17/20024/17/2002 12:00:00 AMPPART
###-#### still needs backflow test 4/17/2002 1:17:42 PM
PLM99-04020 Water and/or Sewer4/17/20024/17/20024/17/2002 12:00:00 AMPPASS
Scheduled by Inspector: 309 On 4/17/2002 1:17:04 PM this was for the back flow valve. 4/17/2002 3:36:41 PM
PLM01-01977 Final4/15/20024/17/20024/17/2002 12:00:00 AMPNH
Scheduled by a contractor via Hello! on 04/15/2002 at 10:47:26. Contact: ###-####.