Inspections for the day of: Monday, April 17, 2006.
Number of inspections: 11
Percentage of inspections complete: 82 %
Percentage of inspections not complete: 18 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD02-02618 FIRE-Conference4/3/20064/10/2006 P 
Follow-up on correction notice. One week was given to start work ending on 4/10/06.
BLD02-02216 FIRE-Conference4/3/20064/10/2006 P 
Follow-up on correction notice. One week was given to start work ending on 4/10/06.
FIR06-00075 INSP-Sprinkler Rough-in4/13/20064/17/20064/17/2006 4:28:51 PMPCANC
todd; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
FIR06-00140 INSP-Sprinkler Rough-in/Hydro4/17/20064/17/20064/17/2006 3:25:27 PMPPART
Heads in hard lids as marked on plans is ok to cover.
FIR05-00895 FIR-Aging Inspection4/17/20064/17/20064/17/2006 3:21:02 PM NR
I spoke to Jim Martin at ###-####, and he is waiting for fire sprinkler plans to be re-approved and then will call in the inspection.
FIR05-00297 INSP-Final Inspection4/14/20064/17/20064/17/2006 3:08:08 PMPFAIL
Basement hydro test failed again. Balldrip did not operate, riser strickers, riser tag and backflow preventor certification still needs to be done. No final inspection performed.
FIR05-00297 INSP-Sprinkler Rough-in/Hydro4/14/20064/17/20064/17/2006 3:07:11 PMAFAIL
Basement hydro test failed again. Balldrip did not operate, riser strickers, riser tag and backflow preventor certification still needs to be done.
FIR06-00051 INSP-Final Inspection4/14/20064/17/20064/17/2006 2:38:12 PMACANC
contractor had not done work yet
FIR06-00092 INSP-Sprinkler Rough-in/Hydro4/14/20064/17/20064/17/2006 10:48:19 AMACANC
Wrong inspection number called in
FIR06-00188 INSP-Sprinkler Rough-in4/14/20064/17/20064/17/2006 10:46:12 AMAPART
sprinkler piping for phase 1 is ok to cover.
FIR06-00252 INSP-Final Inspection4/14/20064/17/20064/17/2006 8:54:42 AMAPASS
Sprinkler piping is ok to cover. I met with the superintendant and went over possible obstructions by fixtures and explained the "three times rule" to him on sprinkler spacing. He will get with Commercial fire with possible changes.