FIR09-00120
| INSP-Final Inspection | 4/16/2009 | 4/17/2009 | 4/17/2009 4:01:31 PM | P | FAIL |
|
|
Todays test was to be for only the riser monitoring portion of the system. Test had to be failed due to the central station not receiving all of the signals such as phone line 1 and 2 troubles. Per Robert this test will be rescheduled for monday.
|
FIR09-00001
| INSP-Final Inspection | 4/17/2009 | 4/17/2009 | 4/17/2009 3:59:39 PM | P | PASS |
|
|
Permit finaled
|
FIR09-00019
| INSP-Final Inspection | 4/16/2009 | 4/17/2009 | 4/17/2009 3:58:51 PM | A | FAIL |
|
|
A trouble signal is needed from the new panel to the existing facp, several strobes are overspaced, an updated map is needed at the existing and the new facp, the existing backflow gate valves need to be adjusted, the existing sprinkler flow switch needs to be tested and as-builts showing the changes need to be provided.
|
FIR08-00831
| INSP-Sprinkler Rough-in/Hydro | 4/15/2009 | 4/17/2009 | 4/17/2009 1:54:01 PM | A | PASS |
|
|
All sprinkler piping on teh second floor can be covered. As-built drawings were provided for the new piping in the overbuild areas and were signed and dated but will need to be submitted to the paln reviewer for approval.
|
FIR08-00830
| INSP-Sprinkler Rough-in/Hydro | 4/15/2009 | 4/17/2009 | 4/17/2009 1:51:32 PM | A | PASS |
|
|
The only item inspected today was the south canopy as marked on the city approved plans. As-bults were provided, dated and signed for this area, that will need to be resubmitted for approval to the plan reviewer. The sprinkler piping as marked in this area is ok to cover.
|
BLD08-02508
| FIRE-Final Inspection | 4/16/2009 | 4/17/2009 | 4/17/2009 11:45:46 AM | A | FAIL |
|
|
All gates (three of them) and the access roadway to be 20'-0" free clearance as per IFC 503.2.1 and 503.6
|
BLD09-00201
| FIRE-Final Inspection | 4/16/2009 | 4/17/2009 | 4/17/2009 11:11:30 AM | A | PASS |
|
|
life safety pased
|