FIR16-00089
| INSP-Sprinkler Rough-in | 4/18/2016 | 4/18/2016 | 4/18/2016 11:27:17 AM | P | PART |
|
|
Partial rough to cover inspection complete for 3rd floor. Notated city approved plans area's that were inspected with red ink/yellow highlighter, area's notated on city approved drawings approved for cover.
|
FIR15-00602
| INSP-Sprinkler Rough-in/Hydro | 4/18/2016 | 4/18/2016 | 4/18/2016 11:24:39 AM | P | PART |
|
|
Southwest underground supply hydrostatic test complete, noorthwest hydro will be completed after underground flush is complete.
|
FIR16-00262
| INSP-Final Inspection | 4/15/2016 | 4/18/2016 | 4/18/2016 9:14:19 AM | A | CANC |
|
|
Not required. Permit finaled satisfactorily on Friday.
|
FIR16-00257
| INSP-Final Inspection | 4/15/2016 | 4/18/2016 | 4/18/2016 8:38:31 AM | A | PASS |
|
|
Final inspection passed/complete
|