Inspections for the day of: Friday, April 19, 1996.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorGerry Varner
TitlePLM-INSPECTOR
Phone #447-7209
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM96-00957 INSP - Sprinkler & Backflow4/18/19964/19/19964/19/1996 12:00:00 AMACANC
04/18/96 323 - DID BY ANOTHER INSPECTOR
PLM96-00964 INSP - Ground work4/19/19964/19/19964/19/1996 12:00:00 AMPPASS
04/19/96 323 - GROUND WORK OK
PLM96-00969 INSP - Sewer line4/19/19964/19/19964/19/1996 12:00:00 AMPPART
04/19/96 323 - READY AT 2:00 ___ OUT SIDE PORTION OF SEWER LINE OK__PART
PLM96-00189 INSP - Final4/19/19964/19/19964/19/1996 12:00:00 AMPCANC
04/19/96 323 - REINSPECTION _STAN HAS THIS INSPECTION
PLM96-00416 INSP - Final4/19/19964/19/19964/19/1996 12:00:00 AMPCANC
04/19/96 323 - THIS IS IN THE BASEMENT..ENTRANCE ON THE SIDE OF HOUSE GARY Z. HAS THIS INSPECTION
PLM96-00895 INSP - Sewer line4/19/19964/19/19964/19/1996 12:00:00 AMPPASS
04/19/96 323 - LATE AS POSSIBLE __ PARTIAL SEWER REPLACEMENT FINAL
PLM96-00943 INSP - Sprinkler & Backflow4/19/19964/19/19964/19/1996 12:00:00 AMPPASS
04/19/96 323 - SPRINKLER VALVE AND DRAIN TIE IN FINAL