FIR16-00253
| INSP-Conference | 4/19/2016 | 4/19/2016 | 4/19/2016 2:02:07 PM | P | DONE |
|
|
Don and I discussed the pendant sprinkler spacing in the dining room. I noted insulation at the roof deck blocking upright heads and possibly overspaced upright against draftstops that are not Dons scope of work but will need addressed prior to a cover inspection being done.
|
BLD16-00509
| FIRE-Final Inspection | 4/19/2016 | 4/19/2016 | 4/19/2016 1:49:43 PM | P | PASS |
|
|
life safety passed. No exit signs marked on plans but two existing are installed
|
FIR15-00907
| INSP-Sprinkler Rough-in/Hydro | 4/19/2016 | 4/19/2016 | 4/19/2016 1:29:40 PM | P | PASS |
|
|
Overhead hydro test (200psi) passed.
|
BLD16-01243
| FIRE-Final Inspection | 4/19/2016 | 4/19/2016 | 4/19/2016 1:28:43 PM | P | FAIL |
|
|
Resubmit plans showing the additional floor area that is being occupied, remove the thumbturn dead bolt (keyed ok) and provide sticker at the exit as discussed.
|
BLD15-04346
| FIRE-Conference | 4/19/2016 | 4/19/2016 | 4/19/2016 11:16:38 AM | P | DONE |
|
|
Met sprinkler contractor and project superintendant and discussed job progress and floor slope in the fire pump room.
|
FIR16-00143
| INSP-Sprinkler Rough-in | 4/19/2016 | 4/19/2016 | 4/19/2016 9:59:08 AM | P | PASS |
|
|
See the city approved plans for location where piping can be covered with todays date.
|
FIR16-00153
| INSP-Final Inspection | 4/19/2016 | 4/19/2016 | 4/19/2016 9:23:34 AM | P | PASS |
|
|
Permit finaled
|
FIR07-00757
| FIR-Aging Inspection | 4/19/2016 | 4/19/2016 | 4/19/2016 8:05:55 AM | | NH |
|
|
Contractor is out of business
|
BLD16-00619
| FIRE-Final Inspection | 4/18/2016 | 4/19/2016 | 4/19/2016 8:04:49 AM | A | PASS |
|
|
Life safety passed. Door hardware is passage but has not been installed since doors have not arrived on site.
|
FIR16-00259
| INSP-Final Inspection | 4/18/2016 | 4/19/2016 | 4/19/2016 8:03:26 AM | A | PASS |
|
|
Permit finaled
|